# How Cabral Gold's 3,000-Tonne-a-Day Mine Is Ramping Up at Cuiú Cuiú

*Cabral poured its first gold in September, sold it above US$4,200 an ounce, and expects to declare commercial production at its Brazilian heap leach this quarter.*

By Élise Galarneau, Small-Cap and Ventures Correspondent

Cabral Gold has crossed four milestones in ten weeks: first pour on 10 September, first sales above US$4,200 an ounce, a new chief operating officer on 17 November and a larger resource on 19 November. The company expects commercial production at its Phase 1 heap leach in the fourth quarter, with the technical report on the new resource due by early January.

## Why This Matters

Cabral has been selling gold from its own mine since its first sale, reported on 30 September. Its next two dated steps, commercial production and the technical report, both fall within about six weeks.

## Key Numbers

- **First gold sales:** over 2,400 oz at more than US$4,200/oz net (release of 30 September 2026.)
- **Phase 1 design rate:** 3,000 tonnes a day, about 1 million tonnes a year (prefeasibility study released 29 July 2025.)
- **Measured and indicated resource:** 998,800 oz at 0.73 g/t (effective 11 November 2026, release of 19 November 2026.)
- **Cash:** C$22,417,212 (at 30 June 2026, interim statements filed 29 August 2026; C$44,957,580 placement closed 24 August 2026.)
- **Gold loan:** C$67,365,273 at fair value (at 30 June 2026; 345 kg of gold borrowed from Precious Metals Yield Fund.)

Cabral Gold is now a gold producer. Its first mine, at Cuiú Cuiú in Brazil, poured gold in September and is ramping up.

The company expects to declare commercial production in the fourth quarter of 2026.

## A small mine built first, on purpose

Cuiú Cuiú sits in the Tapajós region of Pará state, in northern Brazil. Cabral chose to start small. Phase 1 is a heap leach. Crushed ore is stacked on a lined pad and sprinkled with a dilute cyanide solution. The solution dissolves the gold as it trickles through the pile.

The ore is oxide, rock that weathering has softened near surface. It is cheap to dig and easy to leach. The plant is designed for 3,000 tonnes a day, about one million tonnes a year. Ausenco do Brasil led the prefeasibility study, released on 29 July 2025.

That study put initial capital at US$37.7 million and all-in sustaining costs at US$1,210 an ounce. All-in sustaining cost is the full cost of producing an ounce, including the spending needed to keep the mine running. The study's base case assumed gold at US$2,500 an ounce.

## From first pour to first sales

Cabral announced its first gold pour on 10 September 2026. The company reported about 1,130 ounces of doré in that first pour.

Doré is the rough bar a mine pours on site. A refinery then turns it into pure gold.

On 30 September the company reported its first sales. The release said over 2,400 ounces were sold "at an average net realized price in excess of US$4,200 per oz." That is at least US$1,700 an ounce above the US$2,500 base case in the prefeasibility study, which estimated all-in sustaining costs of US$1,210 an ounce. Those costs are a study estimate; the first reported quarter of production will test them.

It called the project "on time and budget" for commercial production in the fourth quarter of 2026.

Commercial production is a formal declaration. It means the mine runs steadily near its design rate. After it, operating costs flow through the income statement as a normal business.

## New operating leadership

On 17 November Cabral named David Londono chief operating officer. He was general manager of the Detour Lake mine in Ontario.

He has also been chief operating officer for the Americas at OceanaGold. He led Mineros S.A. as president and chief executive.

Londono said he enjoys "taking a new mine from first pour to consistent, low-cost production."

John Sestan moved up from vice-president of project development to chief development officer. Chief executive Alan Carter summed up the moment in one line. "Cabral has just become a gold producer."

The release also reported that Phase 1 construction finished "two months ahead of schedule."

## The resource behind the starter mine

Two days later came the larger resource. The release reports measured and indicated ounces up 49 per cent and inferred ounces up 376 per cent on the previous combined estimates, the 2022 primary and 2025 oxide estimates. The weight of the new estimate sits in the hard rock below the oxide.

A mineral resource is a formal estimate of tonnes and grade. It is not yet a mine plan.

Resources come in confidence levels. Measured and indicated are drilled closely enough to support mine planning studies. Inferred is drilled more widely and carries more uncertainty.

| Material | Measured and indicated | Inferred |
| --- | --- | --- |
| Oxide, heap-leachable | 265,600 oz at 0.38 g/t | 210,900 oz at 0.39 g/t |
| Primary hard rock | 733,200 oz at 1.09 g/t (indicated only) | 2,302,000 oz at 1.09 g/t |
| Total | 998,800 oz at 0.73 g/t | 2,512,900 oz at 0.95 g/t |

The estimate has an effective date of 11 November 2026. It assumes gold at US$3,500 an ounce.

VMG Consultoria e Soluções prepared it. Its qualified person, Volodymyr Myadzel, is independent of Cabral. Brian Arkell, Cabral's vice-president of technical services, also approved the technical content as a qualified person.

A qualified person is the professional who signs off on technical disclosure under Canada's National Instrument 43-101.

The oxide side matters most for the mine running today. Oxide measured and indicated ounces rose 21 per cent, and oxide inferred ounces 190 per cent, in the 16 months since the July 2025 oxide estimate.

The release said that growth is expected to support a near-term expansion of Phase 1.

Most of the ounces are in primary rock: 733,200 oz indicated and 2,302,000 oz inferred. The release says Phase 2 will focus on the primary resource. The July 2025 prefeasibility study covered the oxide heap leach only.

## Drilling goes on beside the leach pad

Drilling did not stop when the mine started. The database behind the new estimate holds 149,835 metres in 2,020 holes.

Of those, 604 holes and 46,118 metres were added after the 2022 estimate. All six deposits are open at depth, according to the release.

The last drill release, on 20 October, extended the Central deposit. Hole DDH391 cut 8.2 metres at 2.50 g/t gold from 149.7 metres.

Results for 28 diamond holes and 69 shallower reverse-circulation holes were at the laboratory then. Reverse-circulation drilling returns rock chips rather than solid core, and costs less per metre.

Cabral plans significant infill drilling in 2027. Infill means tighter spacing between holes. It is how inferred ounces can move up into measured and indicated.

## Where the boulder fields come in

Retail discussion of the stock has centred on the boulder fields at Cuiú Cuiú. Some posts claim a geological report described an ancient lake.

Cabral's documents mention boulders in one context. The resource release lists more than 50 peripheral targets "with gold in reconnaissance drill holes, surface trenches and boulder fields."

None of the company releases or the prefeasibility release explains how the boulders formed. Neither the 19 November resource release nor the 29 July 2025 prefeasibility release mentions an ancient lake.

The same goes for talk of a four-million-tonne oxide operation. The company documents describe one million tonnes a year today.

In an interview with BNN Bloomberg on 9 November, Carter spoke of going from one to two million tonnes a year. He also mentioned a study of a second phase.

Carter said he expects to outline plans for a preliminary economic assessment of the second stage.

## The money that built it

Cabral funded construction with a gold loan. It closed in November 2025 with Precious Metals Yield Fund.

The loan is 345 kilograms of gold, valued then at US$45.1 million. Cabral repays it in gold, 39 kilograms a quarter from 31 March 2027, according to the interim statements to 30 June 2026.

At 30 June 2026 the loan was carried at C$67,365,273 at fair value. The value rises with the gold price.

The interim statements for the nine months to 30 June 2026 showed cash of C$22,417,212 at that date. After the quarter, on 24 August, Cabral added C$44,957,580 from a private placement. The buyer was Alpayana S.A.C., a Peruvian miner, which paid for 34,582,754 units at C$1.30. Each unit came with half a warrant at C$1.70, and the placement gave Alpayana 9.99 per cent of the shares.

At 30 June 2026 current liabilities exceeded current assets by C$3,289,875. The statements flag that working-capital deficiency in their going-concern note.

The note refers to a "material uncertainty" that "may cast substantial doubt" on the company continuing as a going concern. The same note says the company "anticipates that it has sufficient funds for its capital requirements up to the commencement of commercial production."

## What comes next

The statements for the year to 30 September 2026 are due by late January. They will be the first to include gold sales.

Until then, the cash figure is the one at 30 June.

On the TSX Venture the shares closed at C$1.23 on 25 November, up C$0.06, or 5.1 per cent, on 306,644 shares, per end-of-day data read at 17:07 ET on TMX Money.

The technical report on the new resource is due on SEDAR+ within 45 days of 19 November, by about 3 January.

Cabral is selling gold from its first mine, and the technical report and the year-end statements are its next two filings.

## Disclosure

**Transparency note.** This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from Cabral Gold Inc. (TSXV: CBR), OceanaGold Corporation (TSX: OGC), Mineros S.A. (TSX: MSA), Alpayana S.A.C. or Precious Metals Yield Fund, or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. Neither The Maple Markets nor the author holds a position in the securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: [Editorial Standards](https://themaplemarkets.ca/en/policies/editorial-standards) · [Financial Disclaimer](https://themaplemarkets.ca/en/policies/financial-disclaimer).

## Sources and references

1. [Cabral Gold: Significant Increase to Mineral Resource Estimate for the Cuiú Cuiú Gold Project (19 November 2026)](https://cabralgold.com/blog/2026/11/19/cabral-gold-announces-significant-increase-to-mineral-resource-estimate-for-the-cuiu-cuiu-gold-project-brazil/)
2. [Cabral Gold: Appointment of Chief Operating Officer and Chief Development Officer (Newsfile, 17 November 2026)](https://www.newsfilecorp.com/release/324343)
3. [Cabral Gold: interim financial statements for the nine months ended 30 June 2026 (filed 29 August 2026)](https://financialfilings.com/filings/cabral-gold-inc/interim-quarterly-report/2026/58347282/)
4. [Cabral Gold: Results of Updated Prefeasibility Study on the Gold-in-Oxide Starter Operation (Newsfile, 29 July 2025)](https://www.newsfilecorp.com/release/260474/Cabral-Gold-Announces-Results-of-Updated-Prefeasibility-Study-on-the-GoldinOxide-Starter-Operation-at-the-Cui-Cui-Gold-Project-Brazil)
5. [Cabral Gold: closing of the gold loan (Newsfile, 26 November 2025)](https://www.newsfilecorp.com/release/276014)
6. [Cabral Gold: First Gold Pour at Phase 1 Mine (10 September 2026)](https://www.webull.com/news/15553775672681472)
7. [Cabral Gold: first gold sales (30 September 2026)](https://www.webull.com/news/15666844969075712)
8. [Cabral Gold: closing of private placement with strategic investor (24 August 2026)](https://investingnews.com/cabral-gold-announces-closing-of-45-million-private-placement-with-strategic-investor/)
9. [Cabral Gold: Expands the Central Gold Deposit (20 October 2026)](https://cabralgold.com/blog/2026/10/20/cabral-gold-expands-the-central-gold-deposit-cuiu-cuiu-gold-district-brazil/)
10. [BNN Bloomberg: Cabral Gold moves into production at Cuiú Cuiú (9 November 2026)](https://www.bnnbloomberg.ca/investment-trends/2026/11/09/cabral-gold-moves-into-production-at-cuiu-cuiu-to-fund-district-scale-growth-in-brazil/)

Canonical: https://themaplemarkets.ca/en/newsroom/cabral-gold-announces-significant-increase-to-mineral-resource-estimate