# Seabridge Gold's Third Quarter: C$102 Million Spent Building KSM

*The 12 November report describes the season with the most onsite work hours in the British Columbia gold-copper project's history, with a power station energized and the access road to the tunnel portal nearly finished.*

By Priya Sandhu, Technology Editor

Seabridge Gold's third-quarter filings of 12 November 2026 show C$102.3 million invested at KSM in three months, almost double a year earlier, with BC Hydro's Treaty Creek Terminal energized and the 13-kilometre access road near completion. A fully drawn US$100 million loan due by 31 December and a court-ordered review of the project's permit status set the next steps.

## Why This Matters

KSM is Seabridge's principal asset, and the third quarter shows it moving from studies into physical construction. The year-end loan maturity and the permit review both resolve within weeks, on dates the company has set out.

## Key Numbers

- **Third-quarter KSM investment:** C$102.3 million (three months to 30 September 2026, against C$52.8 million a year earlier (report to shareholders, 12 November 2026))
- **Cash and cash equivalents:** C$56.3 million (at 30 September 2026, down from C$117.5 million at 31 December 2025 (interim financial statements))
- **Strategic investor loan:** US$100 million, fully drawn (7% a year, due on or before 31 December 2026, payable in cash or shares (interim statements, Note 9; report to shareholders))
- **Shares outstanding:** 108,079,853 (at 12 November 2026 (MD&A))
- **SEA.TO close:** C$35.55, up from C$35.00, volume 166,026 against a 30-day average of 101,270 (13 November 2026, end-of-day data read at 16:57 ET (TMX Money))
- **SRM0 last trade, Frankfurt:** €22.10, 115 shares (13:06 local time on 13 November 2026 (Börse Frankfurt))
- **Spot gold:** US$3,881.70 an ounce bid (16:58 ET on 13 November 2026 (Kitco))
- **Frankfurt listing:** SRM0, WKN A42AD5, ISIN CA8119271028 (new ISIN follows the CUSIP issued when Valor Gold was separated on 3 June 2026 (FinanzNachrichten listing data; company release of 3 June 2026))

Seabridge Gold almost doubled what it invested in the KSM project between July and September, and the grid connection it has waited for was completed and energized, according to the report to shareholders it filed on 12 November 2026. The money went into roads, camps, power and engineering in the mountains of northwestern British Columbia, where KSM sits in the district known as the Golden Triangle.

The quarter's figure was C$102.3 million, against C$52.8 million in the same three months of 2025. Seabridge does not mine anything yet. It holds KSM, a gold and copper deposit it has spent years permitting and studying, and it pays for that work with share sales, notes and loans.

KSM's proven and probable reserves stand at 47.3 million ounces of gold and 7.3 billion pounds of copper in 2.3 billion tonnes at average grades of 0.64 grams of gold a tonne and 0.14 per cent copper, according to the company's July 2026 reserves and resources summary, which draws on the prefeasibility study in the NI 43-101 technical report dated 8 August 2022. A reserve is the part of a deposit a study has shown can be mined at a profit. The MD&A states that a feasibility study, the more detailed study a construction decision rests on, is targeted for completion by the end of 2027. The year's events, in the order they happened, are set out below.

## A new share in June, and a court asks for a second look

The year's first large change was corporate. On 3 June 2026 Seabridge completed the transfer of its Courageous Lake project in the Northwest Territories to a new company, Valor Gold Corp., whose shares went to Seabridge holders. Each old Seabridge share was exchanged for one new Seabridge share plus one Valor share for approximately every 1.957 Seabridge shares held, and the new Seabridge shares took a new CUSIP number, 811927102, on the Toronto and New York exchanges, according to the company's release that day.

A CUSIP is the nine-character code that clearing systems use to identify a security, and the international ISIN is built from it; FinanzNachrichten's listing data show the shares trading in Frankfurt under the symbol SRM0, with WKN A42AD5 and ISIN CA8119271028, the ISIN that follows from the new CUSIP.

Five days later the permitting story moved. KSM holds an Environmental Assessment Certificate, the provincial approval that lets a major project be built, and such a certificate lapses unless the project is "substantially started" by a deadline. The province's Environmental Assessment Office made that determination for KSM on 24 July 2024. On 8 June 2026 the Supreme Court of British Columbia, ruling on a challenge by the Tsetsaut Skii km Lax Ha, ordered the office to reconsider the determination after further consultation with that Nation, according to the third-quarter report.

## A US$100 million loan from a strategic investor in July

On 20 July Seabridge arranged an unsecured loan of up to US$100 million from a party it describes as "a strategic investor". 

The interim financial statements set out the terms: interest at 7 per cent a year, money available until 31 December 2026, and every amount drawn due on or before that date. Seabridge may repay principal and interest in cash, in its own common shares, or in a mix of the two. A share settlement needs Toronto Stock Exchange approval, is priced under the exchange's rules, and cannot leave the lender and its affiliates holding more than 4.9 per cent of the company.

US$50 million, or C$69.9 million, had been drawn by 30 September.

Nine days after the loan was signed came the date that matters most for the permit. The management's discussion and analysis states that the certificate "expires unless the KSM Project was substantially started as of July 29, 2026." Management's own assessment, in the same document, is that "the probability of KSM not retaining the EAC is remote", citing the court ruling and the work done at site since the original determination.

## 350 people at site in August

The summer is where the quarter's spending shows up physically. Five camps supported the 2026 field work and site personnel peaked at more than 350 people in August, the report says, with the highest annual onsite work hours the project has logged and no lost-time incidents in the year to date.

Three pieces of infrastructure moved forward.

- **Power.** BC Hydro completed and energized the Treaty Creek Terminal, the substation that will connect KSM to the provincial grid. Turnover to BC Hydro's operations was formalized in the quarter and final closeout is scheduled before year-end. The report states that "construction costs are aligned with previous forecasts."
- **Access.** The 13-kilometre Upper Treaty Creek Access Road, which will reach the portal of the Saddle tunnel, "neared 100% completion by quarter end". It was built by a joint venture of Lemare Construction and the Treaty Creek Limited Partnership, a 50/50 business owned by the Nisga'a Growth Corporation and the Tahltan Nation Development Corporation.
- **Engineering.** Geotechnical, metallurgical and environmental field programs were completed, preliminary mine planning and plant layout advanced, and work began on a project execution plan and an early contractor engagement plan for 2027.

Over nine months, Seabridge added C$293.4 million to KSM on its balance sheet, most of it recorded as construction in progress, according to the mineral interests note in the interim statements. The project's carrying value reached C$1,470.2 million at 30 September 2026.

## The season's cost, on the 30 September balance sheet

The statements show the cost of that season, and the shift is easiest to see side by side.

| Interim statements | 31 December 2025 | 30 September 2026 |
| --- | --- | --- |
| Cash and cash equivalents | C$117.5 million | C$56.3 million |
| Accounts payable and accrued liabilities | C$17.6 million | C$67.6 million |
| Loan payable | none | C$69.9 million |
| Working capital | C$109.8 million | deficit of C$58.8 million |

The working capital line, meaning current assets less the debts due within a year, turned into a deficit at 30 September 2026 because the loan is classed as current. Seabridge adds the loan back to report "adjusted working capital" of C$11.2 million at 30 September 2026, a measure the MD&A says has no standard definition under IFRS.

The three months to 30 September 2026 also showed a profit of C$6.7 million, or C$0.06 a share. It came mostly from a C$16.2 million remeasurement gain on the company's secured notes, an accounting revaluation of two financings it took on in 2022 and 2023, and it is not cash from operations.

Those notes, with principal of US$225 million and US$150 million, were carried at C$536.9 million at 30 September 2026. The MD&A states that the 2022 note "is to be exchanged at maturity for a 60% gross silver royalty" on KSM, and the MD&A states that the holders' put options become exercisable on 24 March 2028.

New shares came from two sources in 2026. The interim statements record 759,222 shares sold through the at-the-market program for net proceeds of C$35.8 million, at an average price of C$48.15. An at-the-market program lets a company sell new shares gradually into the market at prevailing prices; Seabridge's is now fully used.

Another 698,564 shares were issued as interest on the secured notes. Shares outstanding stood at 108,079,853 on 12 November, according to the MD&A.

As at 30 September 2026, the MD&A also discloses a Canada Revenue Agency matter under which Seabridge may have to indemnify past flow-through share investors for C$10.8 million plus C$4.3 million of interest; no provision has been recorded.

## A hearing, a Wyoming purchase and the second US$50 million

The court heard the outstanding issues on 14 October.

Its decision confirming the June orders, which the company calls the Confirming Decision, had not been released when the report was filed on 12 November. After it is released, the Environmental Assessment Office will take Seabridge's submissions on work done between the original determination and 29 July 2026, draft a report for the company, the Tsetsaut Skii km Lax Ha and other Indigenous groups to review, and then reconsider. The MD&A states that the reconsidered determination "may not be issued until late in the fourth Quarter of 2026."

In October Seabridge also bought the Sierra Madre property in southern Wyoming from Orogen Royalties Inc.: 163 claims for US$300,000, with milestone payments of up to US$2.55 million and royalties retained by Orogen. The report describes it as an early-stage gold project; it is a small commitment beside KSM.

On 2 November the company drew the second US$50 million, "fully utilizing the US$100 million facility," the report says. The whole loan now falls due by 31 December 2026. If it is not settled in shares, the MD&A states, Seabridge "would be required to seek external sources of financing to fund any payments due."

## The partner Seabridge is negotiating with

The company's plan for the step beyond this year runs through a partner. An earn-in joint venture is an arrangement in which a partner pays for an agreed share of a project's development and earns an ownership stake as it does so. "We continue to make progress on a KSM earn-in joint venture with our preferred partner," Rudi Fronk, chair and chief executive, wrote in the report. The MD&A describes the counterparty as "a senior mining company partner" and gives no signing date. The report adds that Seabridge is aligning the 2027 field program with that partner.

On the gold price, management's view in the report is that markets are overestimating the chance of a December rate increase in the United States, and that "the dollar will fall and gold will recover its momentum."

Seabridge shares closed at C$35.55 in Toronto on Friday, a little above the previous close and on heavier volume than their recent average, per end-of-day data read at 16:57 ET on 13 November 2026 (TMX Money).

In Frankfurt, SRM0 last traded at €22.10 on 115 shares that day (Börse Frankfurt); spot gold was bid at US$3,881.70 an ounce at the same hour as the Toronto read (Kitco).

The third quarter is the clearest evidence so far that KSM has entered construction, with a grid connection energized and the tunnel road almost finished. The dated items before year-end are the court's Confirming Decision, the province's reconsidered determination, which the company expects late in the fourth quarter, and the settlement of the loan by 31 December.

Seabridge enters December with its heaviest season of site work completed, and the Treaty Creek closeout and the 2027 contractor plan already under way.

## Disclosure

**Transparency note.** This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from Seabridge Gold Inc. (TSX: SEA), Valor Gold Corp. (TSX: VGC), Orogen Royalties Inc. (TSXV: OGN) or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. Neither The Maple Markets nor the author holds a position in the securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: [Editorial Standards](https://themaplemarkets.ca/en/policies/editorial-standards) · [Financial Disclaimer](https://themaplemarkets.ca/en/policies/financial-disclaimer).

## Sources and references

1. [Seabridge Gold, Report to Shareholders, quarter ended September 30, 2026 (12 November 2026)](https://cdn.prod.website-files.com/5f8f6760f825687e7c1c6508/6af62efaa0271d7cf11e9688_2026%20Q3%20Report%20to%20Shareholders%20-%20FINAL%20November%2012.pdf)
2. [Seabridge Gold, condensed consolidated interim financial statements for the three and nine months ended September 30, 2026](https://cdn.prod.website-files.com/5f8f6760f825687e7c1c6508/6af6334aa659604994caaf7d_FS20260930%20V6.1.pdf)
3. [Seabridge Gold, Management's Discussion and Analysis for the three and nine months ended September 30, 2026](https://cdn.prod.website-files.com/5f8f6760f825687e7c1c6508/6af6334e7fe4fd869a25a3ee_MDA20260930%20V6.1.pdf)
4. [Seabridge Gold, financial reports page](https://www.seabridgegold.com/investors/financial-reports)
5. [Seabridge Gold, "Seabridge Gold Announces Closing of Spin Out of Valor Gold Corp." (3 June 2026)](https://www.seabridgegold.com/press-release/seabridge-gold-announces-closing-of-spin-out-of-valor-gold-corp)
6. [Newsfile, "Seabridge Gold Files Third Quarter 2026 Report to Shareholders, Financial Statements and MD&A" (12 November 2026)](https://www.newsfilecorp.com/release/323831)
7. [Seabridge Gold, Reserves and Resources summary (July 2026)](https://cdn.prod.website-files.com/5f8f6760f825687e7c1c6508/6a63c33441f892ebccab5df5_Reserves-Resources-July%202026%20-%20FINAL.pdf)
8. [FinanzNachrichten, Seabridge Gold release page with Frankfurt listing data (12 November 2026)](https://www.finanznachrichten.de/nachrichten-2026-11/70118631-seabridge-gold-inc-seabridge-gold-files-third-quarter-2026-report-to-shareholders-financial-statements-and-md-a-296.htm)
9. [TMX Money, Seabridge Gold (SEA) key data, end-of-day quote read 13 November 2026](https://money.tmx.com/en/quote/SEA/key-data)
10. [Börse Frankfurt, Seabridge Gold SRM0 (ISIN CA8119271028) quote page, read 13 November 2026](https://www.boerse-frankfurt.de/equity/CA8119271028)
11. [Kitco, precious metals spot prices, read 13 November 2026](https://www.kitco.com/price/precious-metals)

Canonical: https://themaplemarkets.ca/en/newsroom/seabridge-gold-filed-its-third-quarter-2026-report-to-shareholders-its