# 100,000 Ounces a Year Is West Red Lake Gold's New Target

*The November 4 pre-feasibility study puts the working Madsen mill and the higher-grade Rowan deposit into one ten-year plan, two days after the company signed a binding term sheet for up to US$95 million of new debt.*

By Daniel Okoye, Mining and Resources Correspondent

West Red Lake Gold has published one mine plan for its operating Madsen mine and its Rowan deposit, targeting more than 100,000 ounces of gold a year from 2029 to 2034 with a C$764 million after-tax value at the company's price assumptions. It follows a year in which Madsen's mill rate rose each quarter, and a November 2 term sheet for up to US$95 million of debt meant to refinance and extend the company's existing loan.

## Why This Matters

Madsen, in commercial production since January 1, 2026, has reported gold output in every quarter of 2026, and the new study is the first document that sets out how the company intends to grow it. The next filings, the September quarter statements on November 27 and the technical report by mid-December, are where the plan's numbers can be checked in full.

## Key Numbers

- **Integrated PFS after-tax NPV:** C$764 million (at 5 per cent, base-case gold price deck; C$272 million at 20 per cent lower prices (West Red Lake Gold release, November 4, 2026))
- **Target production, 2029 to 2034:** 108,000 oz a year on average (Madsen and Rowan combined, peak 119,000 oz (PFS release, November 4, 2026))
- **2026 production guidance:** 27,000 to 32,000 oz (revised on October 27, 2026 from 35,000 to 45,000 oz; 22,102 oz produced in the first nine months)
- **Proposed credit facility:** up to US$95 million (binding term sheet signed November 2, 2026 with Gunvor USA LLC; definitive agreements pending)
- **Cash:** C$31.2 million (at June 30, 2026, per the condensed interim financial statements approved August 25, 2026)

West Red Lake Gold has completed a single mine plan for the Madsen mine it already runs in Ontario's Red Lake district and for Rowan, a higher-grade deposit that would feed the same mill. The pre-feasibility study, released in November, targets more than 100,000 ounces of gold a year once Rowan is in production.

A pre-feasibility study is the middle of three engineering stages a mining company works through before building or expanding a mine. It is detailed enough to convert part of a deposit into reserves, which are the tonnes an engineer has shown can be mined at a profit under stated prices, and it is the stage at which lenders start to read the numbers closely. For West Red Lake, the study arrived at the end of a year in which the company moved from restarting Madsen to running it. The plan rests on 962,000 ounces of probable reserves and an after-tax value of C$764 million at the company's gold-price assumptions, and it uses a mill that is already built and running.

## Spring: a restarted mine and its first full-year target

Madsen is an underground gold mine with its own permitted mill, which West Red Lake restarted. The company produced 5,667 ounces in the first quarter of 2026, according to its October 27 operations release, mining 572 tonnes a day and milling at the same rate.

The company's first guidance for the full year was 35,000 to 45,000 ounces, built on a planned ramp-up through 2026. The company revised that range on October 27.

## Summer: the mill rate climbs and the quarter turns cash positive

The second quarter was the step up. The October 27 release, which carries the reconciled figures, shows 8,576 ounces produced, with ore mined at 867 tonnes a day and milled at 842.

Revenue for the June quarter was C$49.2 million and net income C$14.7 million, according to the interim financial statements for the period ended June 30, 2026.

All-in sustaining cost, the industry's measure of what each ounce costs once mining, processing, site overheads and the capital needed to keep the mine running are counted, fell to US$3,284 an ounce from US$4,678 in the first quarter, according to the management's discussion and analysis for the period. The same report shows free cash flow of C$9.7 million for the quarter ended June 30, 2026.

The statements show cash of C$31.2 million at June 30, 2026, after C$38.2 million of first-half spending on the mine and its equipment.

At June 30, 2026 the same balance sheet carried the existing Nebari credit facility at C$43.7 million, the loan the November refinancing is meant to replace, and gold-linked notes, a form of debt whose payments are tied to the gold price, at C$62.1 million. Madsen moved into commercial production on January 1, 2026, the statements note, and the company cautions there that "the estimated revenue could be lower than operating and financing costs" and that future financing is not assured.

## September: drilling inside the mine and outside it

Two drill releases in September dealt with the ground the study would later lean on. The first reported gold at Starratt-Olsen, a target near Madsen. The second, on September 22, reported 176.04 grams of gold per tonne over 5.3 metres from the Austin, 955 and 904 areas of the mine itself.

Drill intercepts measure grade across a length of core at one point in the rock. They are what an engineer uses to design stopes, the blocks of ore that are mined one at a time, and they do not by themselves add ounces to a mine plan. The 904 area appears in the study as part of the ground Madsen is scheduled to mine.

## October 27: a better quarter for the mill, a lower target for the year

The third-quarter operations release brought two facts at once. The mill averaged 867 tonnes a day, its highest quarterly rate of the year, after a new secondary crusher lifted the plant's capacity. September produced 3,320 ounces, the best month since the restart.

The company also cut its 2026 guidance to 27,000 to 32,000 ounces from 35,000 to 45,000.

It attributed the change to industry-wide labour challenges and to a ramp-up that runs through the rest of the second half. Mining in the third quarter averaged 710 tonnes a day against 867 in the second quarter, while the mill averaged 867, so the shortfall came from the mine rather than the plant.

The fourth quarter follows directly. The company produced 22,102 ounces in the first nine months of 2026, so landing inside the revised range takes between about 4,900 and 9,900 ounces in the last three. The September monthly figure, run for three months, would sit near the top of that band. The company has not published a fourth-quarter forecast of its own; the range is the gap between its year-to-date production and its annual guidance.

## November 2: debt to replace debt

Six days later the company signed a binding term sheet with Gunvor USA LLC, a subsidiary of Centalion Group (CY) Ltd., for a credit facility of up to US$95 million and an agreement to sell Gunvor all the gold doré Madsen produces. Doré is the unrefined gold-and-silver bar a mine pours on site and ships to a refinery.

The facility has two parts: up to US$65 million in a first tranche and up to US$30 million in a second that carries further conditions. The first tranche has a nine-month holiday before monthly principal payments begin, a five-year term, and interest at one-month SOFR, the US dollar benchmark rate, plus 5.50 per cent. The company said the money would refinance its existing secured loan from Nebari Natural Resources Credit Fund II LP, add working capital for Madsen and could fund development at Rowan.

A term sheet sets the terms both sides intend to sign. The definitive loan, security and offtake agreements were to be negotiated after November 2, and funding depends on due diligence, approvals and those documents being executed. The release gave no closing date. The November 2 document describes a loan and involves no new shares. Chief executive Shane Williams described it as "a more competitive cost of capital and significantly improved repayment terms," and tied the second tranche to Rowan: "The potential second tranche for Rowan aligns with this strategy, providing an additional source of development capital as we advance the project."

The June 30, 2026 statements list 413,947,977 shares outstanding.

The same statements list 21,548,400 warrants exercisable at C$0.68 that expire on November 28, 2026. If all were exercised they would bring in about C$14.7 million.

## November 4: the study

The study combines two deposits that have been described separately until now.

| Item | Madsen | Rowan | Combined |
| --- | --- | --- | --- |
| Probable reserves, million tonnes | 3.40 | 1.01 | 4.41 |
| Reserve grade, g/t gold | 6.06 | 9.23 | 6.79 |
| Contained gold in reserves, ounces | 662,000 | 300,000 | 962,000 |
| Production in the plan | in commercial production since January 1, 2026 | first gold 2029 | 108,000 oz a year on average 2029 to 2034, peak 119,000 oz |

Source: West Red Lake Gold release, November 4, 2026; reserves effective September 1, 2026, estimated at US$2,500 an ounce.

Madsen alone feeds the mill for the first two years. Rowan development begins in 2028 under the company's schedule, with final mine approvals expected by 2029 ahead of first gold.

Rowan ore then travels about 80 kilometres by truck, and the mill runs at 1,350 tonnes a day on a blend of roughly one part Rowan to two parts Madsen. Over ten years the plan recovers about 884,000 ounces.

The study puts the after-tax net present value at C$764 million. Net present value is the plan's future cash flow discounted back to a single figure today, here at 5 per cent a year.

The value depends on the gold price the company assumed, which eases from US$4,597 an ounce in 2027 to a long-term US$3,568 from 2030. At 20 per cent below that deck the value falls to C$272 million, and at 20 per cent above it rises to C$1.245 billion.

Spot gold was bid at US$3,852.30 an ounce late on November 16, 2026, according to Kitco, which places the market above the plan's long-term assumption and below its 2027 figure.

The plan needs C$200 million of growth capital, of which C$39.8 million is the Rowan mine itself. Its all-in sustaining cost over the mine life is US$2,457 an ounce.

The company's own limits are stated in the document. Williams called the plan "a defined base case at a point in time." Rowan's permits are expected by 2029, and the mill needs amendments to its permits for the higher throughput. About 13 per cent of Madsen's planned tonnes come from remnant mining beside historical workings, and the plan assumes a coarser grind than the Madsen plant has run, at a recovery cost the study puts at about 3 per cent. Inferred material at Rowan is treated as waste, and deposits such as Wedge, Russet and Mount Jamie are excluded. The release also assumes the company can raise the capital the plan needs.

## Where Madsen stands on the evidence

Madsen is a producing mine with three reported quarters of 2026 output and a mill that ran at 867 tonnes a day in the third quarter. Its reserves are probable reserves under a pre-feasibility study, which is a real engineering standard and one step short of a full feasibility study. Rowan is a reserve inside a plan, with its mine and permits scheduled for 2028 and 2029.

Measured against those stages, the year has been one of operating progress with one forecast missed. The mill outran the mine, and the guidance cut is a mining-rate problem the company has named and dated. The study is the first time the company has set out, in reserve terms, how a mine producing around 30,000 ounces this year becomes one producing more than three times that.

The reserves were estimated at US$2,500 an ounce, below every year of the plan's price deck.

## The next dates

The September quarter statements and the nine-month results are due after the close on November 27, with a webcast on November 30. The C$0.68 warrants expire on November 28, the day after the results.

The NI 43-101 technical report behind the study is due on SEDAR+ within 45 days of November 4, which places it by about December 19. The definitive Gunvor agreements have no date yet.

The plan's growth depends on Rowan permits due by 2029 and on final documents for the refinancing. In 2026 West Red Lake has taken the Madsen mill to 867 tonnes a day and published a reserve-backed plan for more than 100,000 ounces a year from 2029, and its September-quarter statements follow on November 27.

## Disclosure

**Transparency note.** This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from West Red Lake Gold Mines Ltd. (TSXV: WRLG), Centalion Group (CY) Ltd., Gunvor USA LLC, Nebari Natural Resources Credit Fund II LP or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. Neither The Maple Markets nor the author holds a position in the securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: [Editorial Standards](https://themaplemarkets.ca/en/policies/editorial-standards) · [Financial Disclaimer](https://themaplemarkets.ca/en/policies/financial-disclaimer).

## Sources and references

1. [West Red Lake Gold, Integrated PFS release, November 4, 2026 (GlobeNewswire)](https://www.globenewswire.com/news-release/2026/11/04/3395077/0/en/west-red-lake-gold-announces-integrated-pfs-delivering-c-764-million-post-tax-npv-and-annual-gold-production-of-100-000-ounces-once-rowan-enters-production.html)
2. [West Red Lake Gold, US$95 million credit facility and offtake term sheet, November 2, 2026](https://westredlakegold.com/west-red-lake-gold-signs-us95-million-credit-facility-and-gold-offtake-agreement-with-centalion/)
3. [West Red Lake Gold, Q3 2026 production release, October 27, 2026](https://westredlakegold.com/west-red-lake-gold-reports-q3-2026-production-and-continued-operational-momentum-at-the-madsen-mine/)
4. [West Red Lake Gold, condensed interim consolidated financial statements, six months ended June 30, 2026](https://westredlakegold.com/wp-content/uploads/2026/08/WRLG-Q2-2026-FS-FINAL.pdf)
5. [West Red Lake Gold, management's discussion and analysis, six months ended June 30, 2026](https://westredlakegold.com/wp-content/uploads/2026/08/WRLG-Q2-2026-MDA-FINAL.pdf)
6. [West Red Lake Gold, drill results from the Austin, 955 and 904 areas, September 22, 2026](https://westredlakegold.com/west-red-lake-gold-reports-176-04-g-t-au-over-5-3m-128-32-g-t-au-over-4-5m-and-35-72-g-t-au-over-13-35m-from-austin-955-and-904-complexes/)
7. [West Red Lake Gold, Starratt-Olsen drill results, September 10, 2026](https://westredlakegold.com/west-red-lake-gold-intersects-16-16-g-t-au-over-1-5-metres-and-10-94-g-t-au-over-1-5-metres-at-starratt-olsen-advancing-multi-asset-strategy-at-madsen/)
8. [Kitco, live gold price, read November 16, 2026](https://www.kitco.com/charts/gold)