How Ivanhoe Mines' Shares Reached a New Low After a Copper Guidance Cut
Three weeks after Ivanhoe lowered Kamoa-Kakula's 2027 copper guidance by about a fifth, its shares closed at C$6.07 on November 24, with a new mine plan due in March.
Ivanhoe Mines closed at C$6.07 on the Toronto Stock Exchange on November 24, 2026, down 6.90 per cent and below the C$6.285 52-week low TMX Money listed. On November 3 the company cut Kamoa-Kakula's 2027 copper guidance to 300,000 to 350,000 tonnes from 380,000 to 420,000, citing a delay to stoping on the eastern side of Kakula. The same quarter brought record Kamoa-Kakula revenue above US$1 billion and US$643 million of cash. An updated mine plan is due in March 2027.
By Élise Galarneau6 min read
Dieser Artikel ist derzeit nur auf Englisch verfügbar.

Kamoa-Kakula 2027 copper guidance
300,000 to 350,000 tonnes
previously 380,000 to 420,000; Q3 2026 release, November 3, 2026.
Kamoa-Kakula Q3 2026 revenue
US$1.034 billion
EBITDA US$478 million, 46% margin; Q3 2026 release.
Ivanhoe cash and cash equivalents
US$643 million
at September 30, 2026; down from US$885 million (with short-term deposits) at December 31, 2025; Q3 2026 MD&A.
Platreef phase 2
over 450,000 oz a year design capacity
completion expected Q4 2027; Q3 2026 release.
Close
C$6.07, down 6.90%
November 24, 2026, per end-of-day data read at 16:20 ET; TMX Money.
Kamoa-Kakula will grow more slowly in 2027 than Ivanhoe Mines previously guided. On November 3, 2026, the company cut the mine's 2027 copper guidance to 300,000 to 350,000 tonnes, from 380,000 to 420,000.
Three weeks later the shares are at a new low. Ivanhoe closed at C$6.07 on the Toronto Stock Exchange on November 24, down C$0.45 or 6.90 per cent, per end-of-day data read at 16:20 ET on November 24 from TMX Money. That is below the C$6.285 52-week low the page listed.
The company issued no operating news that day. About 8.88 million shares traded on the TSX and 25.73 million across Canadian venues. Its only release in the week was a November 23 tribute to Dr. Phumzile Mlambo-Ngcuka, a member of its board, who has died.
What changed on November 3
Kamoa-Kakula is a copper mine in the Democratic Republic of Congo, owned jointly by Ivanhoe and Zijin Mining, with a minority stake held by the Congolese government. It is Ivanhoe's largest asset by far.
The third-quarter release reset almost every 2027 number for the mine. Production guidance fell by about a fifth at the midpoint. C1 cash cost is the direct cost of producing a pound of copper at the mine, before sustaining capital, royalties and corporate overhead. Expected 2027 C1 cash costs rose, in the November 3 guidance, to US$2.50 to US$3.00 a pound, from US$2.10 to US$2.50. Capital spending guidance rose to US$950 million to US$1.15 billion, from US$750 million to US$950 million.
The company gave its reasons in the release. "The slower ramp-up in 2027 is mainly due to a delay in the start of stoping on the Eastern side of Kakula from Q4 2027 to late Q1 2028," it said. Stoping is the stage where ore is actually mined out of the underground blocks, after the access tunnels are built. The company also cited "prolonged, elevated diesel prices" and lower grades.
For 2026, Ivanhoe now expects about 290,000 tonnes of copper from Kamoa-Kakula. The earlier guidance was 290,000 to 310,000 tonnes.
| Kamoa-Kakula 2027 guidance | Before November 3 | After November 3 |
|---|---|---|
| Copper production | 380,000 to 420,000 t | 300,000 to 350,000 t |
| C1 cash cost | US$2.10 to US$2.50/lb | US$2.50 to US$3.00/lb |
| Capital spending | US$750 million to US$950 million | US$950 million to US$1.15 billion |
Source: Ivanhoe Mines third-quarter 2026 release, November 3, 2026.
The new ranges are guidance, which is the company's own forecast, and the March plan may move them again in either direction.
The case behind the fall
The bearish reading of the quarter runs like this. Kamoa-Kakula's guidance has now been lowered for both 2026 and 2027, and the reset moves growth further out. The previous 2027 range topped out at 420,000 tonnes; the new one tops out at 350,000.
Cost guidance rose at the same time. A higher cash cost and higher capital spending on lower output mean less free cash per tonne. The on-site smelter, which turns concentrate into copper anode, has run at about 60 per cent of capacity since mid-February, and a 35-day shutdown is planned in the first half of 2027.
The balance sheet has also been drawn down. Cash, cash equivalents and short-term deposits fell by US$242 million in the first nine months of 2026, from US$885 million at December 31, 2025, according to the MD&A. Cash and cash equivalents stood at US$643 million at September 30, 2026. Platreef's phase 2 expansion is still under construction, and copper prices have come off their highs. LME three-month copper fell as low as US$13,210 a tonne on November 16, about 10 per cent below September's record, according to Shanghai Metals Market.
Put together, the argument is that the market is pricing a company with slower growth, higher costs and a smaller cash balance than at the end of 2025.
What the same quarter also showed
The third quarter was also a record in one respect. In the three months to September 30, 2026, Kamoa-Kakula's revenue passed US$1 billion for the first time, at US$1.034 billion, and its EBITDA was US$478 million, a margin of 46 per cent. EBITDA is earnings before interest, tax, depreciation and amortization, a rough measure of cash generated by operations. Ivanhoe reported a profit after tax of US$45 million for the quarter.
The mine produced 76,401 tonnes of copper in the quarter. Concentrator recoveries averaged 89 per cent, and about half the plant's feed came from the western side of Kakula, the part not affected by the eastern delay.
Kipushi, Ivanhoe's zinc mine in the same country, produced a record 77,147 tonnes of zinc in concentrate in the quarter. The company tightened its 2026 Kipushi guidance to 270,000 to 290,000 tonnes, from 240,000 to 290,000.
At Platreef in South Africa, the first-phase plant started producing in November 2025 and is still ramping up. Ivanhoe expects the second phase to be complete in the fourth quarter of 2027, with a design capacity of more than 450,000 ounces a year of platinum, palladium, rhodium and gold. Design capacity is what the plant is built to handle, not a production forecast.
Where the eastern Kakula delay comes from
Kakula is the newer and richer of the two main underground mines at Kamoa-Kakula. Its ore body is mined in blocks, and the company is opening the eastern blocks while the western ones carry most of the load.
Mining those eastern blocks needs new pumping systems to keep the ground dry. "Construction of new de-watering infrastructure is now underway and will be required for access to new mining areas," the third-quarter release says. Until that work is finished, stoping in the east cannot start, and the company now puts that start late in the first quarter of 2028.
The western side is running. About half of the concentrator feed in the third quarter came from there, according to the release. For the whole mine, Ivanhoe expects 2026 C1 cash costs of US$2.60 to US$3.00 a pound.
On the question of new money
The funding position is the other open question. No Ivanhoe document states a plan to raise equity. The statements at September 30, 2026 show US$643 million of cash, and the MD&A records about US$1 million of fees on an unutilised revolving credit facility without stating the facility's size. Platreef's full-year 2026 capital guidance was raised to US$415 million to US$445 million, from US$350 million to US$380 million, which the release attributes to capitalised Phase 1 costs before commercial production. The company has not set out how its cash and the revolving facility match its capital programme for 2027.
Ivanhoe's 2026 capital spending guidance for Kamoa-Kakula was narrowed to US$1.1 billion to US$1.2 billion in the same release, from US$1.1 billion to US$1.4 billion, which trims the top of this year's bill. Kamoa-Kakula's spending is shared with its joint-venture partner, so Ivanhoe carries only its share, an indirect 39.6 per cent according to the MD&A.
At the November 24 close the company was valued at about C$8.66 billion on 1,426,460,924 listed shares, per TMX Money, against a 52-week high share price of C$20.34.
The plan due in March
The company has named the next document. "Updated Kamoa-Kakula life-of-mine plan to be released in March 2027," the third-quarter release says. A life-of-mine plan sets out how much ore a mine will process each year until it closes, at what grade and cost.
That plan will show whether the eastern Kakula delay is a one-quarter slip or a longer reshaping of the mine. Until it lands, the guidance of November 3 is the company's latest word on 2027.
Offenlegung
Transparency note. This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from Ivanhoe Mines Ltd. (TSX: IVN) or Zijin Mining Group Co., Ltd. or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. Neither The Maple Markets nor the author holds a position in the securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: Editorial Standards · Financial Disclaimer.
Weiterlesen
Also in English: How Ivanhoe Mines' Shares Reached a New Low After a Copper Guidance Cut
Bergbau & EnergieC$6.30 zum Wochenschluss bei Ivanhoe Mines, während Kamoa-Kakula auf einen Plan im März wartetIvanhoe Mines schloss am 20. November 2026 an der Börse Toronto bei C$6.30. Die Ergebnisse des Unternehmens vom 3. November beziffern die Produktion von Kamoa-Kakula für 2026 auf rund 290,000 Tonnen Kupfer, senkten die Prognose für 2027 auf 300,000 bis 350,000 Tonnen und legten den März 2027 für einen aktualisierten Plan über die Lebensdauer der Mine fest. Kamoa-Kakula verbuchte einen Rekordquartalsumsatz von US$1,034 Millionen, Ivanhoe verfügte zum 30. September über US$643 Millionen Barmittel, und die benachbarte Ressource Western Forelands enthält nun rund 26.7 Milliarden Pfund Kupfer, der größte Teil davon abgeleitet.Priya Sandhu · 23. November 2026 · 9 min
MakroStürme in Chile und ein langsamerer Kongo-Hochlauf kürzen die Förderung in Kanada notierter KupferproduzentenTeck Resources, Capstone Copper, Ivanhoe Mines und Lundin Mining legten zwischen dem 28. Oktober und dem 4. November ihre Ergebnisse für das dritte Quartal 2026 vor. Schnee, Wind und Stromausfälle in Chile kosteten Teck, Capstone und Lundin Produktion, und Lundin senkte seine Kupferprognose für 2026 auf 285,000 bis 310,000 Tonnen. Ivanhoe kürzte seine Prognose für Kamoa-Kakula für 2027 auf 300,000 bis 350,000 Tonnen, weil der Untertageabbau auf der Ostseite von Kakula nun später beginnt. Die realisierten Kupferpreise reichten von US$6.12 bis US$6.85 je Pfund, und der Großteil der Förderung liegt außerhalb Kanadas.Daniel Okoye · 8. November 2026 · 7 min
Bergbau & EnergieIvanhoe Mines senkt seine Kupferprognose für 2027 um fast ein FünftelIvanhoe Mines legte am 3. November 2026 die Zahlen zum dritten Quartal vor. Kamoa-Kakula produzierte 76,401 Tonnen Kupfer und verbuchte einen Rekordumsatz von US$1.03 Milliarden; die Prognose für 2026 liegt nun bei rund 290,000 Tonnen Kupfer in verkaufsfähigen Produkten, gegenüber einer früheren Spanne von 290,000 bis 310,000 Tonnen Kupfer in Anoden oder Blisterkupfer, und die Prognose für 2027 sank auf 300,000 bis 350,000 Tonnen, weil der Kammerabbau auf der Ostseite von Kakula nun erst Ende Q1 2028 beginnt. Die Barmittel betrugen zum 30. September US$642.7 Millionen.Priya Sandhu · 9. November 2026 · 7 min
Dieser Geschichte folgen
IVN.TO folgen – der nächste Maple-Beitrag zu diesem Unternehmen, dazu der Maple Morning Debrief vor Handelsbeginn.
Folgen und fragen
Mehr von unserer Berichterstattung zu den kanadischen Märkten in Google Top Stories.
Quellen und Verweise (7)
- Ivanhoe Mines: 2026 Third-Quarter Financial Results, Overview of Operations and Exploration Activities, November 3, 2026
- Ivanhoe Mines: management's discussion and analysis, September 30, 2026
- Ivanhoe Mines: 76,401 Tonnes of Copper Produced by Kamoa-Kakula for Q3 2026, October 8, 2026
- Ivanhoe Mines: Mourns the Passing of Dr. Phumzile Mlambo-Ngcuka, November 23, 2026
- TMX Money: Ivanhoe Mines Ltd. (IVN) quote
- Shanghai Metals Market: LME copper hits four-month low, November 17, 2026
- The Maple Markets: Ivanhoe Mines' week and the March plan, November 20, 2026
Diese Analyse zitieren
Bitte The Maple Markets nennen und auf die Originalseite verlinken.
Élise Galarneau (25. November 2026). How Ivanhoe Mines' Shares Reached a New Low After a Copper Guidance Cut. The Maple Markets. https://themaplemarkets.ca/de/newsroom/ivanhoe-mines-set-a-new-closing-low-of-c-6-05-on-24-november-2026-downhttps://themaplemarkets.ca/de/newsroom/ivanhoe-mines-set-a-new-closing-low-of-c-6-05-on-24-november-2026-down