West Red Lake Gold Joins Rowan to Madsen in a 962,000-Ounce Plan
The November 4 pre-feasibility study joins the high-grade Rowan deposit to the operating Madsen mill for a ten-year plan, and the third-quarter financial statements follow on November 27.
West Red Lake Gold's integrated pre-feasibility study, released on November 4, 2026, puts 962,000 ounces of gold in probable reserves across the operating Madsen mine and the Rowan deposit and lays out a ten-year plan averaging 88,000 ounces a year. Madsen produced 22,102 ounces in the first nine months of 2026, the company signed a term sheet for a proposed US$95 million credit facility on November 2, and its third-quarter statements are due on November 27.
By Daniel Okoye7 min read

Probable reserves
962,000 oz at 6.79 g/t
Madsen 662,000 oz and Rowan 300,000 oz, effective September 1, 2026; integrated pre-feasibility study release, November 4, 2026.
After-tax NPV (5%)
C$764 million
at a long-term gold price of US$3,568/oz, discounted to October 1, 2026; same release.
Planned output
88,000 oz a year
ten-year average; 108,000 oz a year from 2029 to 2034; same release.
Cash
C$31.2 million
at June 30, 2026; interim financial statements for the six months ended June 30, 2026.
Proposed credit facility
up to US$95 million
binding term sheet with Gunvor USA LLC signed November 2, 2026; funding subject to definitive agreements.
Under Pure Gold Mining Inc., the Madsen gold mine in Red Lake, Ontario, carried a peak market value above C$1.15 billion in 2021, by the account of a 2023 release from West Red Lake Gold Mines Ltd. Two years later Pure Gold was selling it under court-supervised creditor protection, and West Red Lake bought it, brought it to commercial production and has now completed a study that ties it to a second high-grade deposit.
Creditor protection under the Companies' Creditors Arrangement Act lets a company keep operating while a court supervises its restructuring or sale. In Pure Gold's case the outcome was a sale. West Red Lake's release of April 17, 2023 set the price at C$6.5 million in cash, 28,460,000 shares and a 1.0 per cent royalty on future production, plus deferred payments of up to US$10.0 million.
Three and a half years on, Madsen has a second deposit attached to it. On November 4, 2026 West Red Lake published an integrated pre-feasibility study that feeds ore from its Rowan deposit, about 80 kilometres away by road, into the Madsen mill, and it puts 962,000 ounces of gold in probable reserves. The shares closed at C$0.41 on the TSX Venture Exchange on November 20, 2026, down 1.2 per cent, on 2.21 million shares, per end-of-day data read at 16:21 ET on TMX Money.
Rowan's ore will travel by highway to a mill that already runs
A pre-feasibility study is the engineering and cost study that lets a company convert mineral resources into reserves. Reserves are the tonnes a qualified person judges can be mined at a profit under stated prices and costs; "probable" is the category for reserves resting on indicated rather than measured resources. West Red Lake's study was prepared by SLR Consulting (Canada) Inc. with Fuse Advisors, Knight Piésold and Nordmin Engineering, and its effective date is September 1, 2026.
The reserves split unevenly between the two mines, and the split is the point of the plan.
| Probable reserve, effective September 1, 2026 | Tonnes | Grade | Contained gold |
|---|---|---|---|
| Madsen | 3.40 million | 6.06 g/t | 662,000 oz |
| Rowan | 1.01 million | 9.23 g/t | 300,000 oz |
| Combined | 4.41 million | 6.79 g/t | 962,000 oz |
Rowan carries half again Madsen's grade.
Grade is the gold in each tonne of rock, measured in grams per tonne, and in an underground mine it decides how many ounces each truckload pays for. The study schedules Rowan from 2029 to 2034 at about 500 tonnes a day, with the ore hauled to Madsen on existing roads. Madsen's mill expands to 1,350 tonnes a day over those years and blends one part Rowan ore with roughly two parts from Madsen.
The result is a ten-year plan that recovers about 884,000 ounces, an average of 88,000 a year. In the six years Rowan feeds the mill, output averages 108,000 ounces a year. The release puts the increase in contained reserve ounces at 85 per cent over the 2025 study, which covered Madsen alone.
Shane Williams, the president and chief executive, described the step in the November 4 release as a move to "transition from a single-asset operation to a multi-asset producer in Red Lake." The study leaves out the Wedge, Russet and Mount Jamie resources, the past-producing Starratt-Olsen mine and any extension of Madsen or Rowan at depth.
The economics are priced below what Madsen sold gold for this spring
Net present value is today's worth of the cash a project is expected to produce, after tax, with each future year discounted at a set rate. At a 5 per cent rate, discounted to October 1, 2026, the study puts Madsen and Rowan together at C$764 million. That figure rests on a long-term gold price of US$3,568 an ounce, with higher prices assumed for the first three years of the plan.
The comparison that matters sits in West Red Lake's own statements. Madsen realised an average of US$4,288 an ounce on its gold sales in the second quarter of 2026, according to the company's August 25 results release. The long-term price in the study is about 17 per cent below that.
All-in sustaining cost, or AISC, is the industry's measure of what it costs to keep a mine producing an ounce: site costs, royalties, refining, and the capital spent to sustain output. The study of November 4, 2026 projects US$2,457 an ounce over the mine life and a cash cost of US$1,795.
The capital bill is C$200.4 million of growth spending for Rowan, the mill expansion and the tailings facility, plus C$773.0 million of sustaining capital over the decade, mostly at Madsen. The study gives a discounted payback of 2.2 years. It reports no internal rate of return, because the operation generates positive cash flow in its first year.
The sensitivity table shows how far the value moves with the gold price. With the price 20 per cent lower in every year, the after-tax value falls to C$272 million. With it 10 per cent higher, the value rises to about C$1.0 billion.
These are projections at a point in time, and the company calls them that. The supporting technical report is to be filed on SEDAR+ within 45 days of November 4, which puts it on or before December 19.
Madsen's first producing year came in below the first forecast
West Red Lake announced commercial production at Madsen on January 12, 2026, and the mine produced 22,102 ounces in the first nine months of the year. September was the strongest month since the restart, at 3,320 ounces.
The October 27 production update cut 2026 guidance by about a quarter at the midpoint, to 27,000 to 32,000 ounces. The release gave two reasons. Hiring and keeping skilled underground workers was harder than planned, an industry-wide problem in the company's words, and some remnant pillars next to historic workings were more difficult to extract than expected. The company added specialist contractors and commissioned a secondary crusher in the third quarter, and the mill averaged about 867 tonnes a day.
Subtracting the nine-month total from the revised range leaves roughly 4,900 to 9,900 ounces for the fourth quarter, our calculation from the company's figures. The study has the underground mine ramping to 800 tonnes a day by the end of 2026 and moving into unmined ground deeper in the deposit, including the 904 Complex. The first year has been slower than planned; the plant for the faster ones is in place.
C$31.2 million in cash at June 30, and a lender lined up for the debt
The interim financial statements for the six months ended June 30, 2026 show cash and cash equivalents of C$31.2 million at June 30, 2026, down from C$42.4 million at December 31, 2025. Over those six months Madsen generated C$34.9 million from operations and the company spent C$38.2 million on its mine and plant.
Madsen paid its way in the second quarter. Revenue for the quarter to June 30, 2026 was C$49.2 million, and net income for that quarter was C$14.7 million.
The same balance sheet carries two kinds of borrowing. At June 30, 2026 the credit facility from Nebari Natural Resources Credit Fund II stood at C$43.7 million and the gold-linked notes at C$62.1 million. Gold-linked notes are debt whose repayments rise and fall with the gold price.
Working capital, current assets less current liabilities, was negative C$4.1 million at June 30, 2026, according to the management discussion and analysis for the period. The same document says the company has estimated that revenue from Madsen should be sufficient to meet its operational needs, and notes the risk that it may not be.
On November 2 the company signed a binding term sheet with Gunvor USA LLC, a subsidiary of Centalion Group, for a proposed credit facility of up to US$95 million. The first tranche is up to US$65 million; the second, up to US$30 million, carries further conditions.
The release sets a five-year term with a holiday on principal repayments at the start, interest at one-month SOFR plus 5.50 per cent and first-ranking security over Madsen and Rowan. Gunvor would also buy all of the gold doré the operation produces. The money is intended to refinance the Nebari facility, add working capital and, through the second tranche, help fund Rowan. Funding depends on due diligence, definitive loan and security agreements and approvals, and the company has not yet announced that these are complete.
Retail discussion of the stock this week turned on warrants that expired unexercised. The June 30, 2026 statements record 39,014,020 warrants expiring unexercised in the first half of the year, at a weighted average exercise price of C$1.00. Their expiry added no shares.
The management discussion and analysis counted 414,495,085 common shares on August 25, 2026.
The next dates are set
West Red Lake will report its third-quarter financial and operating results after the market closes on Friday, November 27, 2026, and hold a webcast on Monday, November 30 at 11:00 ET. Those will be the first statements filed since the study and the term sheet.
The Gunvor facility remains a proposal until definitive agreements are signed, and the study's output and value are projections that depend on the gold price and on Rowan's permits, which the company expects by 2029. Madsen has a mill that ran at 867 tonnes a day in the third quarter and a ten-year plan to fill it, with the next set of numbers due on November 27.
Disclosure
Transparency note. This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from West Red Lake Gold Mines Ltd. (TSXV: WRLG), Pure Gold Mining Inc., Gunvor USA LLC, Centalion Group or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. Neither The Maple Markets nor the author holds a position in the securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: Editorial Standards · Financial Disclaimer.
Read next
Auch auf Deutsch: West Red Lake Gold verbindet Rowan und Madsen in einem Plan mit 962,000 Unzen
Mining & Energy100,000 Ounces a Year Is West Red Lake Gold's New TargetWest Red Lake Gold has published one mine plan for its operating Madsen mine and its Rowan deposit, targeting more than 100,000 ounces of gold a year from 2029 to 2034 with a C$764 million after-tax value at the company's price assumptions. It follows a year in which Madsen's mill rate rose each quarter, and a November 2 term sheet for up to US$95 million of debt meant to refinance and extend the company's existing loan.Daniel Okoye · November 17, 2026 · 8 min
Mining & EnergyCabral Gold Lifts Cuiú Cuiú's Measured and Indicated Gold by 49%Cabral Gold's updated resource estimate for Cuiú Cuiú in Brazil, published November 19, 2026, raises Measured and Indicated gold to 998,800 ounces and Inferred gold to 2,512,900 ounces across six deposits, two months after the company poured and sold its first gold from the oxide mine on the same ground. Most of the new ounces are Inferred, and a technical report is due within 45 days.Élise Galarneau · November 20, 2026 · 7 min
Mining & EnergyCabral Gold Hires a Former Detour Lake Manager as Its COOCabral Gold has hired David Londono, a mining engineer who once ran the Detour Lake mine in Ontario and later led Colombian producer Mineros S.A., as chief operating officer, and promoted John Sestan, who built its first mine, to chief development officer. The appointments follow Cabral's first gold pour on September 10 and its first sale of more than 2,400 ounces, with commercial production expected in the fourth quarter of 2026 and a resource update by the end of the year.Élise Galarneau · November 18, 2026 · 7 min
Follow this story
Follow WRLG.V — the next Maple piece on this company, plus the Maple Morning Debrief before the open.
Follow and ask
Get more of our Canadian market coverage in Google Top Stories.
Sources and references (8)
- West Red Lake Gold: Integrated PFS delivering C$764 million post-tax NPV (November 4, 2026)
- West Red Lake Gold: Condensed interim consolidated financial statements for the three and six months ended June 30, 2026
- West Red Lake Gold: Management's discussion and analysis for the three and six months ended June 30, 2026
- West Red Lake Gold: Q3 2026 production release (October 27, 2026)
- West Red Lake Gold: US$95 million credit facility term sheet with Centalion (November 2, 2026)
- West Red Lake Gold: Q2 2026 results release (August 25, 2026)
- West Red Lake Gold: Agreement to acquire the Madsen mine (April 17, 2023)
- TMX Money: WRLG quote page (end-of-day data, November 20, 2026)
Cite this analysis
Please attribute The Maple Markets and link to the original page.
Daniel Okoye (November 20, 2026). West Red Lake Gold Joins Rowan to Madsen in a 962,000-Ounce Plan. The Maple Markets. https://themaplemarkets.ca/en/newsroom/west-red-lake-gold-mines-holds-an-integrated-preliminary-feasibilityhttps://themaplemarkets.ca/en/newsroom/west-red-lake-gold-mines-holds-an-integrated-preliminary-feasibility