Ottawa Conditionally Approves Up to C$14 Million for Fireweed's Mactung Tungsten Project

Ottawa has conditionally approved a second federal contribution for the Yukon deposit, aimed at the metallurgy, tender-ready engineering and processing work that comes before a final investment decision.

Natural Resources Canada has conditionally approved up to C$14.0 million for Fireweed Metals' Mactung tungsten project in Yukon, subject to final due diligence, to fund metallurgical testing, tender-ready engineering and a study of a domestic tungsten processing plant. It sits beside an award of up to US$15.8 million under the US Defense Production Act, a road-planning contribution of up to C$12.9 million and C$47.5 million of cash at September 30, with the feasibility study due in early 2027.

By Priya Sandhu6 min read

Ottawa Conditionally Approves Up to C$14 Million for Fireweed's Mactung Tungsten Project
Maple Markets

NRCan contribution

up to C$14.0 million

conditionally approved under the Global Partnerships Initiative, subject to final due diligence (Fireweed release, November 16, 2026).

U.S. Defense Production Act award

up to US$15.8 million

awarded December 12, 2024 to take Mactung to a final investment decision (interim statements, September 30, 2026).

Cash and cash equivalents

C$47,510,119

at September 30, 2026, unaudited interim statements.

Indicated resource

41,487,000 tonnes at 0.73% WO3

effective July 28, 2023 (Fireweed project page).

Frankfurt listing

M0G, WKN A3DQAX, ISIN CA31833F1045

Deutsche Börse listing page, read November 16, 2026.

Ottawa has conditionally agreed to fund part of the last stretch of work between Mactung and a mine decision. Fireweed Metals secured conditional approval on November 16, 2026 for up to C$14.0 million from Natural Resources Canada's Global Partnerships Initiative, to advance the Yukon tungsten project toward a final investment decision, subject to final due diligence.

The money is for named work. The release lists metallurgical test programs, engineering designs advanced to a tender-ready stage, and an assessment of midstream processing, including a possible plant to make ammonium paratungstate. The processing assessment is new to Mactung's funded work.

A conditional contribution, with no commercial covenants anticipated

The award is a government contribution: money paid against eligible costs as the work is done, which is how Fireweed's earlier Canadian and U.S. awards appear in its statements, as reimbursements. No shares are issued for it. Two points frame it. The approval is conditional, so the agreement is not yet signed, and the company describes the amount as a ceiling: "up to" C$14.0 million.

The release adds that the funding commitment "is not anticipated to include any commercial covenants or conditions" that would restrict Fireweed's business or its future sales of tungsten products. Fireweed's management will run the funded work and send periodic progress reports to the program's administrators.

Government support for a strategic mineral sometimes comes with a say over who may buy the output; on the company's description, this contribution is not expected to carry one.

The second Canadian cheque, and the American one before it

Mactung already had public money behind it, from two governments.

AwardCeilingDateWhat it pays for
U.S. Defense Production Act, Title IIIup to US$15.8 millionawarded December 12, 2024work to take Mactung to a final investment decision, including the new feasibility study
NRCan, Critical Minerals Infrastructure Fund (now the First and Last Mile Fund)up to C$12.9 millionsigned August 2025planning for road and power improvements on the North Canol corridor, the project's main overland route
NRCan, Global Partnerships Initiativeup to C$14.0 millionconditionally approved November 16, 2026metallurgy, tender-ready engineering and a midstream processing assessment

The American money is already flowing. The interim statements for the nine months to September 30, 2026 record C$10,004,599 of Defense Production Act reimbursements against Mactung spending. Another C$3,727,548 arrived after the quarter closed.

The new award joins a program two governments were already paying into, and for the first time the funded work extends past the mine to what happens to the concentrate after it leaves the site.

What Mactung is

Mactung sits on the Yukon and Northwest Territories border, inside Fireweed's 100 per cent owned Macpass district of 985 square kilometres.

Fireweed's current mineral resource estimate, effective July 28, 2023, reports 41,487,000 tonnes of indicated resources at 0.73 per cent tungsten trioxide, with a further 12,247,000 tonnes of inferred resources at 0.59 per cent.

An indicated resource is one drilled closely enough to support mine planning; an inferred resource is a less certain estimate that needs more drilling before it can be used that way. Neither category is a reserve, which is the portion shown to be economic to mine in a feasibility study.

The project has been studied before. A feasibility study was completed in 2009, and Mactung completed its environmental assessment in 2014, according to Fireweed's March 9, 2026 release. In his statement on November 16, Energy and Natural Resources Minister Tim Hodgson called it "one of the world's largest undeveloped high-grade tungsten deposits". Fireweed itself, citing S&P Global Market Intelligence's Capital IQ database, has described it as unmatched in grade and scale.

Why a processing plant is in the scope

Tungsten leaves most mines as a concentrate. Ammonium paratungstate, or APT, is the refined chemical intermediate that manufacturers turn into tungsten carbide, alloys and other products used in cutting tools, aerospace and defence equipment. Selling concentrate means relying on someone else's refinery.

Fireweed's release sets out the supply picture in the company's own words. It says North America has had no primary tungsten production since 2015, that China accounts for over 80 per cent of global primary production, and that China has introduced several measures restricting tungsten exports. Fireweed's stated commercial aim is to become the preferred and primary supplier of tungsten concentrate to North American midstream processors.

The new award lets the company test a step beyond that aim. The release says the work will assess "midstream processing opportunities", including the possible development of an APT facility. The release describes an assessment; no decision on a facility has been announced.

The work already under way

The money joins a feasibility study that started in March. Fireweed named Wood Canada as lead consultant, with SLR Consulting updating the resource, Ausenco on the process plant and metallurgy, Worley on mine design, and Knight Piésold and Lorax on geotechnical and water work.

The 2026 field season has finished. According to the management discussion and analysis for the quarter to September 30, 2026, crews drilled 1,439 metres of geotechnical boreholes, dug 31 test pits and completed 841 metres of dual-purpose drilling for groundwater and resource studies. The same document says the feasibility study "remains on schedule for completion in early 2027". Fireweed's March 9 release said the study will support mine licence applications expected in 2027.

What the balance sheet carries into the study

Fireweed reported cash and cash equivalents of C$47,510,119 at September 30, 2026, in its unaudited interim statements. Working capital was C$51,402,523 at September 30, 2026, against current liabilities of C$7,799,656.

Most of that cash came from one financing. On April 2, 2026 Fireweed closed a non-brokered private placement of 14,704,140 shares at C$4.18 each, for gross proceeds of C$61,463,305. JX Advanced Metals, which the April 2 release describes as a global leader in advanced materials with deep expertise in high-purity materials, including tungsten, bought 11,343,294 of those shares, about 5.0 per cent of the company, and received an investor rights agreement that includes anti-dilution, offtake and participation rights. Trusts settled by the late Adolf H. Lundin took up their share and held about 22.9 per cent at closing.

The cost of the work shows in the same statements. Operating activities used C$40,375,480 in the nine months to September 30, 2026, a period that included Fireweed's main field season across its projects. The interim statements show 227,083,299 shares outstanding at that date.

The statements also carry the company's own caution. Note 1 says additional financing will be required for further exploration and development, which "may indicate the existence of material uncertainty that may cast significant doubt" about the company's ability to continue as a going concern. The same note sets that beside working capital of C$51.4 million at September 30, 2026. Building a mine at Mactung would need capital on a different scale, and the feasibility study is the document that will put a number on it.

Where the shares trade

Fireweed moved from the TSX Venture Exchange to the Toronto Stock Exchange on November 5, 2026 under the same symbol, FWZ. It also trades on the OTCQX as FWEDF and in Frankfurt as M0G, with WKN A3DQAX and ISIN CA31833F1045, as Deutsche Börse's listing page shows.

On November 16 the Toronto shares closed at C$2.04, down 0.97 per cent from C$2.06 on 390,060 shares traded on the TSX, per end-of-day data from TMX Money read at 16:57 ET on November 16, 2026. At the filed share count that puts the company's market value at about C$463.2 million.

The question the study now carries

The record since March is a sequence of completed steps: consultants engaged, a C$61.5 million financing closed with a strategic tungsten buyer on the register, a field season finished, a senior listing secured and now a second federal contribution approved. The feasibility study is due in early 2027 and the licence applications are expected to follow in the same year.

The processing assessment the new contribution funds is the work that will show whether Mactung's tungsten could be refined to APT in Canada rather than shipped as concentrate.

Disclosure

Transparency note. This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from Fireweed Metals Corp. (TSX: FWZ), JX Advanced Metals Corporation or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. Neither The Maple Markets nor the author holds a position in the securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: Editorial Standards · Financial Disclaimer.

Read next

Auch auf Deutsch: Ottawa sagt Fireweeds Wolfram-Projekt Mactung unter Bedingungen bis zu C$14 Millionen zu

  1. Mining & EnergyVault Strategic in Nevada: Four Months of Work on One Tungsten PropertyOn July 3, 2026 Vault Strategic Mining set aside two other tungsten options to concentrate on War Bond, a 1950s tungsten producer in western Nevada. Since then it has reported surface sampling, flown a 73.6 line-kilometre magnetic survey, closed a C$1.5 million placement and started a maiden NI 43-101 technical report. The company has not yet dated that report; its statements for the six months to November 30, 2026 are the next scheduled filing.Daniel Okoye · November 4, 2026 · 7 min
  2. Mining & EnergyVault Strategic Plans a Technical Report and Drill Permit Applications at War BondVault Strategic Mining closed a C$1.5 million placement on September 29, 2026 and on October 19 released processed maps from a 73.6 line-kilometre drone magnetic survey at War Bond, its historical tungsten property in western Nevada. The company says the data will feed its first NI 43-101 technical report, follow-up surface work and drill permit applications. The survey maps rock magnetism rather than tungsten grade, and no dates for those steps have been published.Daniel Okoye · October 29, 2026 · 6 min
  3. Mining & EnergyHow First Phosphate Plans to Mine Battery Phosphate in Quebec by 2030First Phosphate presented its October 2026 plan at Kinvestor Day: a 204.7-million-tonne measured and indicated phosphate resource at Bégin-Lamarche in Quebec, definitive offtake agreements, provincial fast-track status, about C$21.5 million in signed federal contributions, a feasibility study due in the first quarter of 2027 and commercial production targeted for 2030. It held C$19.9 million in cash at August 31, 2026.Élise Galarneau · October 27, 2026 · 6 min

Follow this story

Follow FWZ.TO — the next Maple piece on this company, plus the Maple Morning Debrief before the open.

FWZ.TO

By subscribing you agree to receive the Maple Morning Debrief and occasional editorial emails from The Maple Index Inc. Unsubscribe any time with one click.

Follow and ask

Add The Maple Markets to your Google sources

Get more of our Canadian market coverage in Google Top Stories.

Priya SandhuTechnology Editor · 8 years covering Canadian technology issuersMore by Priya Sandhu
Sources and references (8)

Discussion

Comments are written by readers, not by The Maple Markets newsroom. They are moderated, unverified, and are not investment advice.

Join the discussion

Create a free account to comment, reply and follow the companies you care about.

We use necessary cookies to run the site and, only with your permission, analytics cookies to understand what readers use. Cookie policy