C$700 Million of KSM Work Goes Into B.C.'s Second Look at Seabridge
Seabridge Gold says KSM's environmental certificate stands after a B.C. court confirmed on November 18 that the project's substantially started designation was quashed and must be reconsidered.
Seabridge Gold said on November 19, 2026 that KSM's environmental assessment certificate is unaffected by the B.C. Supreme Court's latest ruling, and that the province's reconsideration of the project's substantially started designation will now weigh more than C$700 million of construction work. The court confirmed the original designation was quashed and that deeper consultation with the Tsetsaut Skii km Lax Ha is required. Seabridge shares closed at C$25.92 in Toronto, down 29.26 per cent.
By Priya Sandhu8 min read

KSM construction investment
more than C$700 million
through July 29, 2026, up from C$444 million at the July 2024 designation; submitted to the Environmental Assessment Office in September (Seabridge release, November 19, 2026)
Strategic investor loan
US$100 million, fully drawn
7% a year, due on or before December 31, 2026, payable in cash or shares within a 4.9% ownership cap (MD&A for the quarter to September 30, 2026)
Cash and cash equivalents
C$56.3 million
at September 30, 2026, against C$117.5 million at December 31, 2025 (MD&A, filed November 12, 2026)
KSM proven and probable reserves
47.3 million oz gold, 7.3 billion lb copper
July 2026 reserves and resources summary (Seabridge)
SEA.TO close
C$25.92
down 29.26% from C$36.64 on 925,652 shares traded on the TSX, November 19, 2026; end-of-day data read at 16:57 ET (TMX Money)
Seabridge Gold has completed two more years of construction at KSM since British Columbia first found the project substantially started, and that work is now in front of the province's regulators. Seabridge says the project's environmental assessment certificate is unaffected while they weigh it.
Seabridge Gold said in its release of November 19, 2026 that the court's latest ruling "settling the Court Orders" leaves the KSM environmental assessment certificate unaffected. The same ruling confirmed that the province's July 2024 finding that KSM was substantially started was quashed when the court sent it back for reconsideration in June.
Seabridge shares closed at C$25.92 in Toronto on November 19, 2026, down 29.26 per cent from the previous close of C$36.64, on 925,652 shares traded on the Toronto Stock Exchange, per end-of-day data read at 16:57 ET on November 19, 2026 (TMX Money).
A certificate, a deadline and a designation
Three provincial instruments sit behind the day's headlines, and they are easy to run together.
An environmental assessment certificate is the approval British Columbia grants before a major project can be built. KSM, a gold and copper deposit in the Golden Triangle district of northwestern B.C., holds one. A certificate carries a deadline: it lapses unless the project is "substantially started" by a set date, and for KSM that date was July 29, 2026, according to Seabridge's management's discussion and analysis (MD&A) for the quarter to September 30, 2026. The substantially started designation is the province's finding that the deadline was met. The Environmental Assessment Office made it for KSM on July 24, 2024.
On June 8, 2026 the court, ruling on a petition by the Tsetsaut Skii km Lax Ha, ordered the office to reconsider that designation after a further 90 days of consultation with the Nation, which ended on September 28. The parties then disagreed over what the June orders meant, and argued it out at a hearing on October 14.
The ruling released this week settles that disagreement. Seabridge's release states that the court ruled the June order had quashed the designation, dismissed the separate petition by SkeenaWild Conservation Trust "without a ruling on the reasonableness" of the designation, and ruled on how much consultation with the Tsetsaut Skii km Lax Ha the reconsideration requires.
The certificate itself was not part of the order. "If, after its reconsideration of the SSD, the EAO again concludes the KSM Project was substantially started, the KSM environmental assessment certificate will continue in place and not be subject to expiry," the company's release says.
What KSM looks like now, against what it looked like in 2024
Seabridge's case for the reconsideration rests on the work done since 2024.
The company's November 19 release says the office will consider the work completed between July 24, 2024 and July 29, 2026, and that this work raised the construction investment at KSM from C$444 million to more than C$700 million. The release gives the figures without a currency label; Seabridge reports in Canadian dollars. Its September 22, 2026 release set out the office's process for weighing that new information, including a draft report that Seabridge, the Tsetsaut Skii km Lax Ha and other Indigenous groups will review.
The third quarter shows what that money bought. Seabridge's report for the three months to September 30, 2026 records BC Hydro's Treaty Creek Terminal completed and energized to connect the site to the provincial grid, and the 13-kilometre access road to the Saddle tunnel portal close to finished. Site personnel peaked at more than 350 people in August. Maple's report on that quarter, published on November 16, covers the spending in detail.
KSM's proven and probable reserves are 47.3 million ounces of gold and 7.3 billion pounds of copper, according to the company's July 2026 reserves and resources summary. A reserve is the part of a deposit that a study has shown can be mined at a profit.
Spot gold was bid at US$3,635.80 an ounce at 16:29 ET on November 19, 2026, down 2.40 per cent on the day, according to Kitco Metals.
Seabridge chair and chief executive Rudi Fronk said in the November 19 release that "the legal status of KSM has not changed as of the November Ruling." He added that the company has "the full support of the principal First Nations who have recognized traditional territory and Treaty rights, respectively, in the area of KSM and with whom we have impact benefit agreements." The release names them as the Tahltan and Nisga'a Nations.
The strongest case against a quick answer
The other side of the ruling deserves its full weight, because it sets the timetable.
The Tsetsaut Skii km Lax Ha issued its own release on November 19 through CNW. It says Justice Emily Burke confirmed on November 18 that the designation was quashed for lack of consultation with the Nation, that she did not rule on reasonableness because the consultation ground was enough, and that the province must now engage in "deep consultation", including on potential impacts to the Nation's territory. The release states that "there is no specific consultation end date" and that a challenge on reasonableness remains open. Its counsel, Ryan Beaton, said the decision confirms that Seabridge and the province had been "misinterpreting and downplaying" the June ruling.
The Nation's chief, Darlene Simpson, said in the same release that the Nation "is not against responsible resource development" and named its concern: KSM's planned tailings facility, which she described as a wet design. The same release says the Gitxsan Huwilp Government, a neighbouring Nation, withdrew its support for KSM after the June ruling until the Tsetsaut Skii km Lax Ha is properly consulted.
Consultation with no end date can outlast the province's own estimate. The company's MD&A had already said the reconsidered designation "may not be issued until late in the fourth Quarter of 2026", and that estimate was written before the court defined the consultation as deep. A second legal ground was left untested. And on the meaning of the June order, the court sided with the Nation's reading.
What the court did and did not decide
Neither party's account of the ruling says the court found that KSM was not substantially started. The Nation's release says the reasonableness question was not reached. Seabridge's release says the SkeenaWild petition was dismissed without a ruling on it. The question goes back to the office that answered it in 2024, with a larger body of work to weigh.
The MD&A also notes that a designation can be made after the expiry date has passed. "In respect of other projects a substantially started determination (as of the expiry date) was made several months after the relevant expiry date," it says. On the company's account of the province's practice, a longer process would delay the determination rather than end the certificate.
Management's own assessment, written in the MD&A before the ruling, is that "the probability of KSM not retaining the EAC is remote", citing the original application, the province's review, the court ruling and the work done since. The company said in Thursday's release that it will ask the office whether the ruling changes its timetable and is "encouraging the EAO to conclude it promptly."
The loan that falls due on December 31
The second date in front of Seabridge is financial, and the court ruling bears on it through the share price.
On July 20 Seabridge arranged an unsecured loan of up to US$100 million from a strategic investor, at 7 per cent a year compounded monthly, according to the MD&A. It drew the second US$50 million on November 2, using the full facility, and every amount is due on or before December 31, 2026. Seabridge may repay in cash, in its own shares, or in a mix.
The MD&A sets the conditions for paying in shares. The issue price is the greater of 92.5 per cent of the 20-day volume-weighted average trading price and the minimum the Toronto Stock Exchange allows, and the lender and its affiliates cannot own more than 4.9 per cent of Seabridge after the issue. "To the extent these requirements are not satisfied, settlement must be made in cash," it says.
The price at which a full share settlement still fits under that cap can be worked from the MD&A's own figures, assuming the lender holds no Seabridge shares today.
| Step | Figure | Basis |
|---|---|---|
| Shares outstanding, November 12, 2026 | 108,079,853 | MD&A |
| Most new shares the lender can take at 4.9% | about 5.57 million | 4.9 ÷ 95.1 of the count |
| Loan principal in Canadian dollars | about C$140 million | MD&A translates US$50 million as C$70 million |
| Issue price that settles it in full | about C$25.14 | principal ÷ shares |
| 20-day average that issue price implies | about C$27.18 | issue price ÷ 92.5% |
The table is a rough guide. Accrued interest, the exchange rate on the settlement date and any shares the lender already owns all move it, and the lender's existing holding is not disclosed.
Seabridge's MD&A sets out the alternative if shares cannot settle the whole amount: the company "would be required to seek external sources of financing to fund any payments due, such as obtaining replacement royalty arrangements or raising additional capital." Seabridge held cash and cash equivalents of C$56.3 million at September 30, 2026, according to the MD&A. Total liabilities were C$715.3 million at September 30, 2026, most of them the two secured notes, which mature in later years. The MD&A also reports adjusted working capital of C$11.2 million at September 30, 2026, a measure that assumes the loan is settled in shares.
Rudi Fronk wrote in the third-quarter report that Seabridge continues "to make progress on a KSM earn-in joint venture with our preferred partner". An earn-in is an arrangement in which a partner pays for part of a project's development and earns a stake as it goes. No signing date has been given.
Where Seabridge goes from here
The ruling moved the date on which Seabridge can say KSM's certificate is secure, and it left the substance of the question where it was: with the province, and with a project whose construction investment rose from C$444 million to more than C$700 million between July 2024 and July 2026, on the company's figures.
The company has named its next steps. It will ask the Environmental Assessment Office whether Thursday's ruling changes the reconsideration timetable and press for a prompt decision, and it must settle the US$100 million loan by December 31. On site, the third-quarter report schedules Treaty Creek's final closeout with BC Hydro before year-end, and work on an early contractor engagement plan for the 2027 season has begun.
Disclosure
Transparency note. This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from Seabridge Gold Inc. (TSX: SEA) or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. Neither The Maple Markets nor the author holds a position in the securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: Editorial Standards · Financial Disclaimer.
Read next
Auch auf Deutsch: C$700 Millionen an KSM-Arbeit fließen in B.C.s zweite Prüfung von Seabridge ein
Mining & EnergySeabridge Gold's Third Quarter: C$102 Million Spent Building KSMSeabridge Gold's third-quarter filings of 12 November 2026 show C$102.3 million invested at KSM in three months, almost double a year earlier, with BC Hydro's Treaty Creek Terminal energized and the 13-kilometre access road near completion. A fully drawn US$100 million loan due by 31 December and a court-ordered review of the project's permit status set the next steps.Priya Sandhu · November 16, 2026 · 8 min
Mining & EnergyNisga'a and Tahltan Nations Back Seabridge's KSM Bid, and Its Shares Rise 11%On November 23, 2026 the Nisga'a Nation and the Tahltan Nation stated their support for Seabridge Gold's KSM project and for the province's substantial start decision, four days after a B.C. Supreme Court ruling confirmed that the 2024 designation had been quashed and sent back for reconsideration. Seabridge has put more than C$700 million of work at KSM in front of the Environmental Assessment Office, which has set no date for its new decision.Priya Sandhu · November 24, 2026 · 6 min
Mining & EnergyB.C. Conservatives Win a Majority Promising 120-Day Permits for Major ProjectsBritish Columbia elected a Conservative majority on October 24, 2026, by the projections of The Canadian Press and CTV News, with seat counts preliminary overnight. Premier-designate Lorne Doerkson has promised a 120 Day Permitting Act for major projects, red tape cut back to 2017 levels and the repeal of DRIPA. He inherits a record the outgoing government reports as five mines permitted and a mining backlog cut by half, along with a 2025 court ruling on DRIPA and mineral claims.Élise Galarneau · October 25, 2026 · 9 min
Follow this story
Follow SEA.TO — the next Maple piece on this company, plus the Maple Morning Debrief before the open.
Follow and ask
Get more of our Canadian market coverage in Google Top Stories.
Sources and references (10)
- Seabridge Gold: Court Decision on Court Orders Leaves Environmental Assessment Approval Unaffected but Confirms Substantially Started Determination for Seabridge Gold's KSM Project in British Columbia was Quashed (November 19, 2026)
- Seabridge Gold: Management's Discussion and Analysis for the three and nine months ended September 30, 2026 (filed November 12, 2026)
- Seabridge Gold: Third Quarter 2026 Report to Shareholders (November 12, 2026)
- Seabridge Gold: Interim Financial Statements for the period ended September 30, 2026
- Tsetsaut Skii km Lax Ha Nation via CNW: B.C. Supreme Court Confirms Seabridge's KSM Substantial Start Determination Quashed (November 19, 2026)
- Seabridge Gold: Substantially Started Designation Review on KSM Being Progressed by BC's EAO (September 22, 2026)
- Seabridge Gold: Reserves and Resources summary (July 2026)
- TMX Money: SEA quote page
- Kitco Metals: live gold price, read 16:29 ET on November 19, 2026
- The Maple Markets: Seabridge Gold's Third Quarter: C$102 Million Spent Building KSM (November 16, 2026)
Cite this analysis
Please attribute The Maple Markets and link to the original page.
Priya Sandhu (November 20, 2026). C$700 Million of KSM Work Goes Into B.C.'s Second Look at Seabridge. The Maple Markets. https://themaplemarkets.ca/en/newsroom/seabridge-gold-tsx-addressed-the-b-c-supreme-court-s-orders-on-the-ksmhttps://themaplemarkets.ca/en/newsroom/seabridge-gold-tsx-addressed-the-b-c-supreme-court-s-orders-on-the-ksm