Eldorado Gold Runs Four Tailings Filter Presses at Its Skouries Mine
Four presses are the number Eldorado says Skouries needs for commercial production, which it expects late this quarter, with an updated technical report to follow in early 2027.
Eldorado Gold said on 23 November that four of the six tailings filter presses at Skouries, its copper-gold mine in northern Greece, are running. Four is the count the company says commercial production on sulphide ore requires. It expects that milestone late in the fourth quarter, the last two presses in early December, and an updated technical report in the first quarter of 2027.
By Élise Galarneau7 min read

Filter presses running
4 of 6
four are what Eldorado says commercial production on sulphide ore requires, five for nameplate throughput; release of November 23, 2026.
Skouries project capital
about US$1.425 billion
total estimate, of which US$1.379 billion was invested at September 30, 2026; MD&A filed October 28, 2026.
2026 Skouries gold guidance
10,000 to 35,000 oz
cut from 60,000 to 100,000 oz on October 28, 2026 after a slower ramp-up.
Cash and equivalents
US$396.8 million
at September 30, 2026, excluding US$71.9 million restricted for term-loan repayments; MD&A filed October 28, 2026.
Frankfurt listing
ELO1 · WKN A2PA9H · ISIN CA2849025093
quoted in Frankfurt; Deutsche Börse listing page read November 26, 2026.
Skouries now has four tailings filter presses running. Eldorado Gold said so in a release dated November 23, 2026, and four is the number the company says its new copper-gold mine in northern Greece needs before it can be declared in commercial production.
The company expects that declaration late in the fourth quarter. It also said it will file an updated technical report for Skouries in the first quarter of 2027, with a new resource model, new metal price assumptions and new production, cost and capital estimates.
Why a mine in Greece needs presses that squeeze its waste dry
Every mill leaves behind tailings, the finely ground rock that remains once the copper and gold have been floated off into concentrate. Many mines pump that slurry behind a dam. Skouries does something else: it presses the water out and stacks the waste as a damp, compacted solid.
A filter press is the machine that does the squeezing. Slurry goes in, water is forced out through cloth panels, and what comes out can be moved by conveyor and placed in layers. The design takes less land and recovers water for the plant. It also sets the pace. If the presses cannot keep up, the mill cannot run faster than the waste can be handled. That is the plain reason this equipment, rather than the drills or the crusher, has been the step the ramp-up has turned on.
Four of six, and the count the company tied to commercial production
The facility holds six presses supplied by Metso. Five are meant to run and one is an installed spare, so maintenance can happen without slowing the mill. According to the November 23 release, four operating presses are required for commercial production on sulphide ore and five are required to reach nameplate throughput, the plant's full design rate.
In general industry usage, commercial production is a declaration a company makes when a mine is running at a sustainable share of its design rate. Before it, the costs of running the plant are added to the cost of building it. After it, they flow through the income statement like any producing mine's.
"With four filter presses now operational, we have achieved another important milestone in the ramp-up of Skouries," chief executive Christian Milau said in the release. He added that the company remains focused on progressing the ramp-up toward commercial production, "which we expect late this quarter."
The two remaining presses are expected to be operational in early December, the release said.
A slower start than the company planned
In its third-quarter results of October 28, 2026, the company cut its 2026 gold production guidance for Skouries to 10,000 to 35,000 ounces, from 60,000 to 100,000 ounces, because the ramp-up had been slower than expected. Milau said then that the ramp-up "has taken longer and cost more than we expected, and it is important that we acknowledge that directly."
At that date two of the six presses were running, and the company expected the other four to be commissioned in November. Four were running by November 23, and the last two now carry an early-December date. The company gave late in the fourth quarter as its target for commercial production in both documents.
Other steps were already behind the mine by October. First copper-gold concentrate came on September 8, 2026, and the site switched to permanent grid power on September 28, after which the temporary generators were removed, according to the third-quarter release. At September 30, 2026 the stockpiles held about 4.8 million tonnes of ore containing an estimated 176,000 ounces of gold, according to the company.
The October revision, the company said, reflected the timing of the ramp-up and did not change its expectations for Skouries' longer-term design capacity.
What the last stretch costs, and the money behind it
Most of the building money has already gone in. The figures below are from Eldorado's management's discussion and analysis (MD&A) for the quarter ended September 30, 2026, filed on October 28, 2026; accelerated operational capital is the operating spending the company capitalises before commercial production is declared.
| Item | Amount | Date |
|---|---|---|
| Skouries project capital, total estimate | about US$1.425 billion | estimate of October 28, 2026 |
| Project capital invested | US$1.379 billion | at September 30, 2026 |
| Accelerated operational capital, expected | US$390 million | estimate of October 28, 2026 |
| Accelerated operational capital, spent | US$285.6 million | at September 30, 2026 |
| Cash and cash equivalents | US$396.8 million | at September 30, 2026 |
Subtracting the second line from the first leaves roughly US$46 million of project capital to spend from September 30. Up to US$30 million more may be incurred depending on when commercial production is declared, the company said, and it may be booked as project capital, accelerated operational capital, sustaining or growth capital. In the same MD&A it attributed the increase in the Skouries project capital estimate to higher contractor requirements to complete construction and commissioning, the extended use of temporary generators before connection to grid power, and additional owner's and execution costs tied to the longer commissioning period.
The cash figure excludes US$71.9 million of restricted cash held for repayments on the Skouries term loans, which were fully drawn at September 30, 2026. On August 12, 2026 the company raised the availability of its senior secured credit facility to US$600 million. On its current schedule and cost assumptions, Eldorado said in the MD&A, Skouries "remains fully funded through available cash, operating cash flow and existing debt facilities."
The 2027 technical report will reset the mine's numbers
The most recent technical study for Skouries dates from January 2022. That feasibility study described a 20-year mine producing about 240,000 gold-equivalent ounces a year on average, roughly 140,000 ounces of gold plus copper, according to the third-quarter release.
A technical report is the formal document, signed by qualified persons, that a Canadian-listed miner files to support its resource, reserve and production figures. Eldorado said the update due in the first quarter of 2027 will carry an updated resource model and metal price assumptions, together with updated production, operating cost and capital estimates "reflecting the transition of Skouries from development into operations."
So the 2022 figures are the ones that stand until then. The new report will be the first set of numbers written with the mine running, and it may move them in either direction: the company's own forward-looking statements name the resource model, the metal prices and the cost estimates as items that could differ materially from current estimates.
A mine with a European label and a Frankfurt line
Skouries sits on the Halkidiki peninsula, and the company says it is designated a Strategic Project under the European Union's Critical Raw Materials Act. The concentrate is sold under offtake agreements that, according to the third-quarter release, cover all expected Skouries production for the next two years, with more agreements in process through 2029. The company also described the market for copper-gold concentrate as highly competitive.
Eldorado's shares trade in Toronto as ELD and in New York as EGO. In Germany they are quoted in Frankfurt under the symbol ELO1, WKN A2PA9H and ISIN CA2849025093, according to Deutsche Börse's listing page read on November 26, 2026.
In Toronto the shares closed at C$40.11 on November 26, 2026, up C$0.79 or 2.01 per cent on 170,170 shares, per end-of-day data from TMX Money read at 16:20 ET, on a day when US markets were closed for Thanksgiving.
On November 26, 2026, front-month COMEX gold futures traded at US$3,566.20 an ounce and front-month COMEX copper futures at US$5.348 a pound, per Investing.com historical data read at 17:01 ET (a thin holiday session). For comparison, Eldorado realised an average of US$4,326 an ounce sold in the third quarter of 2026, and its gold-equivalent figures for 2026 to 2028 assume US$4,000 an ounce of gold and US$5.00 a pound of copper, according to the October 28 release.
The dates the company has set itself
Skouries is not Eldorado's only start-up this quarter. McIlvenna Bay, the Saskatchewan copper-zinc mine that came with the Foran Mining acquisition in April, also has a late-fourth-quarter target for commercial production. The board declared a fourth-quarter dividend of US$0.075 a share on October 28, payable on December 15.
For Skouries, the company has put three markers on the calendar. The fifth and sixth presses in early December. Commercial production late in the quarter. The updated technical report in the first quarter of 2027.
The first completes the press hall's design of five operating units and one installed spare. The second is the moment the mine's costs start counting as a producer's.
The third is the first full set of Skouries production, cost and capital estimates prepared with the mine in operation.
Disclosure
Transparency note. This is an independent due-diligence analysis produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from Eldorado Gold Corporation (TSX: ELD), Metso Oyj or Foran Mining Corporation, or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. Neither The Maple Markets nor the author holds a position in the securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: Editorial Standards · Financial Disclaimer.
Read next
Auch auf Deutsch: Eldorado Gold betreibt vier Filterpressen für Tailings in seiner Mine Skouries
Mining & EnergyEldorado Gold Lowers Its 2026 Forecast as Skouries Starts Up in GreeceEldorado Gold's third-quarter report, released on 28 October 2026, records first concentrate at Skouries in northern Greece, permanent grid power on site and commercial production expected late in the fourth quarter. The company lowered its 2026 gold forecast to 425,000 to 475,000 ounces from 495,000 to 600,000, raised the Skouries capital estimate to about US$1.425 billion and ended September with US$396.8 million of cash, which it says leaves the project fully funded.Priya Sandhu · October 30, 2026 · 7 min
Mining & EnergyNisga'a and Tahltan Nations Back Seabridge's KSM Bid, and Its Shares Rise 11%On November 23, 2026 the Nisga'a Nation and the Tahltan Nation stated their support for Seabridge Gold's KSM project and for the province's substantial start decision, four days after a B.C. Supreme Court ruling confirmed that the 2024 designation had been quashed and sent back for reconsideration. Seabridge has put more than C$700 million of work at KSM in front of the Environmental Assessment Office, which has set no date for its new decision.Priya Sandhu · November 24, 2026 · 6 min
Mining & EnergyC$700 Million of KSM Work Goes Into B.C.'s Second Look at SeabridgeSeabridge Gold said on November 19, 2026 that KSM's environmental assessment certificate is unaffected by the B.C. Supreme Court's latest ruling, and that the province's reconsideration of the project's substantially started designation will now weigh more than C$700 million of construction work. The court confirmed the original designation was quashed and that deeper consultation with the Tsetsaut Skii km Lax Ha is required. Seabridge shares closed at C$25.92 in Toronto, down 29.26 per cent.Priya Sandhu · November 20, 2026 · 8 min
Follow this story
Follow ELD.TO — the next Maple piece on this company, plus the Maple Morning Debrief before the open.
Follow and ask
Get more of our Canadian market coverage in Google Top Stories.
Sources and references (7)
- Eldorado Gold: Four Tailings Filter Presses Operational at Skouries; Updated Technical Report to be Filed Q1 2027 (November 23, 2026)
- Eldorado Gold: MD&A for the three and nine months ended September 30, 2026 (filed October 28, 2026; SEDAR+ and Form 6-K Exhibit 99.2)
- Eldorado Gold: Q3 2026 Financial and Operational Results and Updated 2026 Guidance (October 28, 2026), Form 6-K Exhibit 99.1
- Deutsche Börse: Eldorado Gold Corp. listing (ELO1, WKN A2PA9H, ISIN CA2849025093)
- TMX Money: ELD quote
- Investing.com: Gold futures historical data (COMEX, read November 26, 2026, 17:01 ET)
- Investing.com: Copper futures historical data (COMEX, read November 26, 2026, 17:01 ET)
Cite this analysis
Please attribute The Maple Markets and link to the original page.
Élise Galarneau (November 27, 2026). Eldorado Gold Runs Four Tailings Filter Presses at Its Skouries Mine. The Maple Markets. https://themaplemarkets.ca/en/newsroom/eldorado-gold-tsx-reported-on-23-november-2026-that-four-tailingshttps://themaplemarkets.ca/en/newsroom/eldorado-gold-tsx-reported-on-23-november-2026-that-four-tailings