Ivanhoe Raises Kamoa-Kakula Copper Output 19% as Guidance Falls

The third quarter was the strongest of Ivanhoe's year at its Congolese copper complex, and the same release carries a 2026 target the company now expects to meet only at its lower end.

Ivanhoe Mines reported 76,401 tonnes of copper in saleable products from Kamoa-Kakula for the third quarter of 2026, up from 64,328 tonnes in the second. The shares fell 4.1 per cent to C$11.13 in Toronto on the day. The same release puts 2026 output at 290,000 to 310,000 tonnes and says production is trending toward the lower end, against the 380,000 to 420,000 tonnes the company guided for 2026 in December 2025.

By Priya Sandhu7 min read

Ivanhoe Raises Kamoa-Kakula Copper Output 19% as Guidance Falls
Maple Markets

Q3 2026 copper, Kamoa-Kakula

76,401 tonnes in saleable products

up about 19 per cent on 64,328 tonnes in Q2 2026, per the company release dated October 8, 2026

2026 guidance

290,000 to 310,000 tonnes, trending to the lower end

against 380,000 to 420,000 tonnes guided for 2026 on December 3, 2025, both company releases

Smelter utilisation

about 60 per cent of 500,000 tonnes a year design capacity

concentrate inventory rose from about 40,000 to about 43,000 tonnes over the quarter, per the October 8, 2026 release

Toronto close, October 8, 2026

C$11.13, down 4.1 per cent on 2.9 million shares

15-minute delayed market data read after the close, secondary market data not verified against filings

Frankfurt listing

FSE symbol IYAA, WKN A1W4VG, ISIN CA46579R1047

10,044 shares and about €71,000 traded on Tradegate on October 8, 2026, against roughly C$32.5 million in Toronto

Ivanhoe Mines, which trades in Toronto under the symbol IVN, told the market on October 8, 2026 that its Kamoa-Kakula complex in the Democratic Republic of Congo had produced 76,401 tonnes of copper in saleable products over the third quarter. It was the company's strongest quarter of the year.

The shares fell anyway. Ivanhoe closed at C$11.13 in Toronto that afternoon, down 48 cents or 4.1 per cent on the day, on 2.9 million shares against a 30-day average of about 3.8 million, per 15-minute delayed market data read after the close on October 8, 2026. Quarterly output was up roughly 19 per cent on the 64,328 tonnes reported for the second quarter. Both facts are in the same release, and they are not in conflict, because they measure different things.

The quarter went up and the year came down

The same release states Ivanhoe's current target for the full year: 290,000 to 310,000 tonnes of copper, with production "trending towards the lower end" of that range.

Ten months earlier, in a release dated December 3, 2025, Ivanhoe announced that Kamoa-Kakula would produce 380,000 to 420,000 tonnes in 2026 and 500,000 to 540,000 tonnes in 2027. Measured against the midpoints, the 2026 target has come down by roughly a quarter, and the company is now pointing at the bottom of the reduced range rather than the middle of it.

That is the number a share price responds to. A single quarter tells you how a mine performed between July and September. A guidance range tells you what the company believes the next several quarters will deliver, and it is the figure analysts carry into their models for the year after. Ivanhoe's recovery from the May 2025 seismic event at Kakula, which flooded part of the underground workings and forced a redesign, is visibly working at the quarterly level. It has not yet restored the annual number.

Three figures describe a plant that is not full

The detail underneath the headline tonnage is where the ramp-up is legible.

Across all three concentrators, Ivanhoe milled 3,493,000 tonnes of ore in the three months to September 30, 2026 at an average feed grade of 2.22 per cent copper, recovering 87.6 per cent of it into 68,188 tonnes of copper in concentrate. The second quarter was 2,968,000 tonnes at 2.39 per cent and 87.4 per cent recovery, for 61,134 tonnes. More rock went through the plant at a slightly lower grade, and the recovery held.

Recovery is the share of the metal present in the ore that the plant actually captures; the rest reports to tailings and is lost. Ivanhoe completed modifications to its Phase 1 and Phase 2 concentrators in July under a programme it calls Project 95, and reported a record average recovery of 89 per cent for the three months to September 30, 2026 as a result. On the volumes above, each percentage point of recovery is worth roughly 780 tonnes of copper a quarter, so the engineering is not cosmetic.

The smelter is the constraint that has not moved. Ivanhoe says the on-site smelter ran at about 60 per cent of its 500,000-tonne-a-year design capacity over the quarter to September 30, 2026. According to the release, of the 76,401 tonnes of saleable copper, 61,506 tonnes came out as anode from that smelter, 2,347 tonnes as blister from third-party toll treatment, and the remainder as slag concentrate and high-grade fines. The company disclosed that concentrate inventory rose from about 40,000 tonnes at the start of the quarter to about 43,000 tonnes at the end, which means the complex is still making concentrate faster than it is converting it.

The solar plant exists, and it is a cost item

Retail discussion of the release has centred on the power project, so it is worth checking against the document rather than the enthusiasm.

The release confirms it. The hybrid solar and battery facility at Kamoa-Kakula reached full ramp-up in late September 2026 and now supplies 60 megawatts of continuous baseload power. Peak photovoltaic capacity is 433 megawatts, the company stated, paired with 1,107 megawatt-hours of battery storage. The two 30-megawatt plants are owned and operated by CrossBoundary Energy and Green World Energie rather than by Ivanhoe, and power purchase agreements are in place to double on-site solar to 120 megawatts within 18 months.

What it buys is fuel. Ivanhoe reported that diesel generator consumption fell about 40 per cent in September against July. Solar at a Congolese mine is an operating cost measure before it is anything else, and its effect will appear in the cash cost per pound in the third-quarter financial statements, not in the tonnage figure. Those statements are due after the market closes on November 3, 2026. The production release carries no balance sheet, no cost figure and no revenue.

Kipushi is ahead of plan and Platreef is behind it

Ivanhoe's other two assets ran in opposite directions, and the release treats both plainly.

At Kipushi, the high-grade zinc mine also in the Democratic Republic of Congo, the concentrator produced a record 77,147 tonnes of zinc in concentrate in the quarter to September 30, 2026, up 10 per cent on the second quarter, from 193,581 tonnes of ore at a feed grade of 41.58 per cent zinc and a recovery of 96.02 per cent. Annualised, that is about 309,000 tonnes against 2026 guidance of 240,000 to 290,000 tonnes, and Ivanhoe says output is tracking toward the upper end.

Platreef, the palladium, platinum, nickel, copper, rhodium and gold mine in South Africa, is the opposite case. Its Phase 1 concentrator started on November 18, 2025 and has not reached commercial production, the accounting threshold at which a mine is deemed to be operating as intended and its output stops being capitalised. In the three months to September 30, 2026 it milled 99,391 tonnes at 62.4 per cent recovery for 4,552 ounces of platinum-group metals plus gold, bringing cumulative output to roughly 8,483 ounces. The Phase 2 expansion to 3.3 million tonnes a year is scheduled for completion at the end of 2027, and Shaft #2 is not expected to hoist ore until the end of 2029.

The German line quotes the price; Toronto sets it

Ivanhoe is quoted on the Frankfurt Stock Exchange under the symbol IYAA, German securities identification number A1W4VG, with the international identifier CA46579R1047. Deutsche Börse's own listing page showed all three as of October 8, 2026, and the company repeats the Frankfurt symbol and the identifier in its own wire boilerplate.

The listing matters for access, not for price discovery, and the volumes say why. Tradegate showed 10,044 Ivanhoe shares changing hands on October 8, 2026 for turnover of about €71,000. Toronto did 2.9 million shares at a volume-weighted average of C$11.22, or roughly C$32.5 million. The European line is a convenience for anyone whose account cannot reach the Toronto exchange directly. The price it shows is the Toronto price translated into euros a few hours later.

What the print leaves open

Three things in this release will be tested in November rather than settled now.

The first is cost. A 19 per cent lift in quarterly copper with recovery holding and diesel consumption down 40 per cent should show up as a lower unit cash cost, and the third-quarter statements on 3 November are where that becomes a number instead of an inference.

The second is the smelter. At 60 per cent utilisation with concentrate inventory building, the bottleneck between what Kamoa-Kakula mines and what it can sell has not cleared, and a fourth quarter that draws the 43,000-tonne stockpile down would say more about the recovery than another production record.

The third is the 2027 range. Ivanhoe has not restated the 500,000 to 540,000 tonnes it guided for 2027 in December 2025, and the gap between that number and a 2026 year finishing near 290,000 tonnes is the question the November call has to answer.

The quarter was good. The year it belongs to got smaller on the same page.

Transparency note. This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from Ivanhoe Mines Ltd. (TSX: IVN) or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. The Maple Markets and its authors may hold positions in securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: Editorial Standards · Financial Disclaimer.

Read next

Auch auf Deutsch: Ivanhoe steigert die Kupferproduktion um 19% und senkt die Jahresprognose

  1. Mining and ResourcesTwo of the Three Cost Figures Circulating About Ivanhoe Mines Are Not in Its FilingsIvanhoe Mines issued no release this week, and the cost figures being traded around its shares come from memory of a conference call. One of the three checks out against the filings. The company reports C1 cash cost and does not report all-in sustaining cost at all, which makes most of the peer comparisons being drawn a comparison of two different measures. The gap between them can be priced from Ivanhoe's own capital guidance.Priya Sandhu · September 25, 2026 · 8 min
  2. Mining and ResourcesEldorado Gold Connects Skouries to the Greek Grid, 20 Days After First ConcentrateEldorado Gold reported on 28 September 2026 that its Skouries copper and gold mine in northern Greece is permanently connected to the Greek national power grid. The release carries no throughput, grade or recovery figure, and it does not change the company's stated schedule of commercial production in the fourth quarter of 2026. About US$1.315 billion is Eldorado's own estimate of total Skouries capital to that point, of which US$1.270 billion had been spent by 30 June 2026.Priya Sandhu · September 29, 2026 · 6 min
  3. Mining and ResourcesTalon Metals Sells Nickel Today From a Mine With Reserves to 2030, and Tamarack Is Still in ScopingTalon Metals closed at C$8.37 on September 9, 2026, up 9.7 per cent on a day with no company news. Since January it has owned the Eagle mine in Michigan, the only active primary nickel mine in the United States, and it reported US$51.5 million of second-quarter revenue on August 13, 2026. The technical report released April 30, 2026 puts Eagle's proven and probable reserves at 3,486 kilotonnes and ends mining in the second half of 2030. Tamarack, the larger asset, is at environmental scoping.Priya Sandhu · September 10, 2026 · 7 min

Follow this story

Follow IVN.TO — the next Maple piece on this company, plus the Maple Morning Debrief before the open.

IVN.TO

By subscribing you agree to receive the Maple Morning Debrief and occasional editorial emails from The Maple Index Inc. Unsubscribe any time with one click.

Follow and ask

Add The Maple Markets to your Google sources

Get more of our Canadian market coverage in Google Top Stories.

Opinion

This article expresses the author's personal views, is separate from news reporting and is not investment advice.

Disclosure

Transparency note. This is an independent due-diligence analysis and editorial opinion piece produced by The Maple Markets editorial desk. It is not sponsored, promoted or commissioned, and no compensation of any kind has been received from Ivanhoe Mines Ltd. (TSX: IVN) or any party acting on their behalf. The analysis is based on public disclosure available as of the publish date; every figure is attributed to its primary source. The Maple Markets and its authors may hold positions in securities mentioned; nothing here is a recommendation to buy, sell or hold any security, and readers should not treat it as investment advice. Past disclosure does not guarantee future results. Policies: Editorial Standards · Financial Disclaimer. See the Financial Disclaimer.

Priya SandhuTechnology Editor · 8 years covering Canadian technology issuersMore by Priya Sandhu
Sources and references (5)
  1. Ivanhoe Mines Reports 76,401 Tonnes of Copper Produced by Kamoa-Kakula for Q3 2026, company release dated October 8, 2026
  2. Ivanhoe Mines Announces Kamoa-Kakula Copper Production Guidance for 2026 and 2027 as Recovery Plan Advances, Newsfile release dated December 3, 2025
  3. Tradegate order book for ISIN CA46579R1047, read October 8, 2026
  4. Deutsche Börse listing page for Ivanhoe Mines A, read October 8, 2026
  5. Ivanhoe Mines Reports 64,328 Tonnes of Copper Produced by Kamoa-Kakula in Q2 2026, Newsfile release

Cite this analysis

Please attribute The Maple Markets and link to the original page.

Priya Sandhu (October 9, 2026). Ivanhoe Raises Kamoa-Kakula Copper Output 19% as Guidance Falls. The Maple Markets. https://themaplemarkets.ca/en/newsroom/ivanhoe-mines-seventy-six-thousand-tonnes-and-a-four-per-cent-fall-what
https://themaplemarkets.ca/en/newsroom/ivanhoe-mines-seventy-six-thousand-tonnes-and-a-four-per-cent-fall-what

Discussion

Comments are written by readers, not by The Maple Markets newsroom. They are moderated, unverified, and are not investment advice.